โ˜• Support Us โ˜•
[๐Ÿ‡ง๐Ÿ‡ฉ] - Corruption Watch | Page 35 | PKDefense

[๐Ÿ‡ง๐Ÿ‡ฉ] Corruption Watch

Reply (Scroll)
Press space to scroll through posts
G Bangladesh Defense
[๐Ÿ‡ง๐Ÿ‡ฉ] Corruption Watch
341
11K
More threads by Saif


TIB finds misappropriation of Tk 2,926.88cr
25 December, 2025, 00:07

1766625949291.webp


The country incurred extra expenditure of about Tk 2,926.88 crore because of about 1.5 times higher than the actual cost of power generation from solar plants, according to a study conducted by the Transparency International Bangladesh, an anti-corruption watchdog.

The study report was launched at an event at the TIB office in the capital Dhaka on Wednesday.

The study titled โ€˜Generating Power from Renewable Energy in Bangladesh: Governance Challenges and Way Forwardโ€™ showed that while Tk 8 crore a megawatt was required for solar power projects according to the Bangladesh Power Development Board, but the six projects under the study had an average estimated cost of Tk 13.8 crore a megawatt.

This means Tk 2,926.88 crore of state resources were wasted through inflated cost estimates, said TIB executive director Iftekharuzzaman at the report unveiling event.

To a query, he said that the study period was limited to the power purchase deals signed by the Awami League regime before being ousted on August 5, 2004, in the wake of a mass uprising.

The Quick Enhancement of Electricity and Energy Supply (Special Provision) Act, 2010, which was misused by the AL regime to sign inflated power purchase agreements on political consideration, was scrapped by the interim government that assumed power on August 8, 2024.

Some 37 renewable energy projects out of total 42 power plants approved by the AL were cancelled by the interim government.

The AL failed to implement the Bangladeshโ€™s Renewable Energy Policy 2008, as the target of getting 10 per cent total electricity from renewable sources by 2020 was missed for too much emphasis on costly fossil fuels.

Bangladeshโ€™s current electricity installed capacity, comprising contributions from both on-grid and off-grid sources, is 28,616.48 megawatts, of which only 1,314.70MW or four per cent come from renewable energy sources.

In the past month, the government approved a dozen solar power plants through competitive biddings.

Iftekharuzzaman said that they would examine the current projects in the future studies.

Responding to a question, the TIB executive director said that the reform initiatives by the interim government since the ouster of the AL regime on the state affairs should not be compared with the reforms in the power and energy sector.

It will take more than two to three years to mend the damage made during the AL regime to the crucial sector, he said.

The average electricity tariff of the selected renewable energy projects in this study is $0.124 per kWh.

In comparison, the average tariff in the neighbouring countries is significantly lower โ€” $0.03 in India, $0.032 in Pakistan and $0.045 in China.

Thus, the tariff in Bangladesh is nearly four times higher than in these countries.

The report highlighted that the interests of the fossil fuel lobby were being protected by marginalising renewable energy in the energy sectorโ€™s master plans, resulting in the failure to realise the vast potential of renewable energy.

The TIB has proposed 15 recommendations to address the existing institutional and policy challenges and build a sustainable and transparent energy system.

The recommendations include immediate cancelation of the existing fossil fuel-dependent energy master plan and implementing a new master plan based on the principles of reducing fossil fuel use and increasing the share of renewable energy in the energy mix.

Formulation of a realistic road map for power generation from renewable sources with uniform targets in all existing policies, including the Renewable Energy Policy 2025, has also been suggested.

Besides, amendment to the Power Act 2018 to provide a legal basis for power generation from renewable energy and providing clear instructions on the transmission, supply, and distribution of generated power through national or alternative grids is among the recommendations.

TIB energy governance coordinator Newazul Moula and assistant coordinator Ashna Islam presented the report.​
 

Corruption threatens clean energy drive
TIB study on solar power projects raises concerns

1766798678879.webp


The transition to clean energy has emerged as an urgent priority for Bangladesh, yet it is disheartening to learn of rampant corruption and exploitation within the sector. A recent Transparency International Bangladesh (TIB) study has revealed that around TK 250 crore has been siphoned off through corruption in land acquisition and compensation in five solar projects, with irregularities spanning every stage from approval to completion. The study also highlights a significant gap between official cost estimates and actual spending.

These projects were designed to deliver affordable clean power and are already in operation. Landowners interviewed for the study alleged that coercive measures were used to pressure them to sell land at dismally low prices, and in some cases, they did not receive their promised compensation at all. Another six projects examined by the TIB show that their combined cost was Tk 6,970 crore, far above the Tk 4,043 crore that would have been expected as per the Bangladesh Power Development Board's estimate of the average costs of setting up solar plants. In other words, about Tk 2,926 crore was overestimated compared to actual costs. Alarmingly, the study has found that the average electricity tariff of these projects is about $0.124 per kilowatt-hour, which is significantly higher than tariffs in our neighbouring countries.

According to the TIB, a syndicate of plant officials, local land registration officials, union and upazila land office staff, middlemen, local public representatives, and even members of parliament were involved in the corruption. From the outset, vested interest groups exerted influence over policymaking and strategy formulation. The same networks reappeared during land acquisition and environmental clearance, leading to coordinated manipulation of compensation, leasing arrangements, and approval processes.

Such story of corruption during Awami League's tenure is widely known, but its impact on the renewable energy sector should particularly alarm policymakers. Renewables now account for about five percent of total generation capacity, with solar contributing more than 80 percent of that share. Solar remains a largely untapped resource to this day. Experts note that diversifying our solar approachesโ€”such as floating photovoltaics, agrivoltaics, and advanced PV technologiesโ€”can expand capacity without displacing farmers or inflating costs, which can also address a lot of the irregularities identified by the study.

The interim government has set ambitious targets to raise the share of renewables to 20 percent by 2030 and 30 percent by 2041. But intention or initiation alone cannot deliver results. Current and future authorities must ensure proper execution as well. Land acquisition processes must be transparent, project costs must be subjected to timely review, and tariffs must be determined fairly. The promise of solar power will only be real if it meets proper planning and execution.​
 

Members Online

Latest Posts

Latest Posts