Saif
Senior Member
- Joined
- Jan 24, 2024
- Messages
- 22,387
- Likes
- 9,875
- Nation

- Axis Group

Costs of two MRT projects set to soar
Costs of two of the upcoming projects for the construction of mass rapid transit lines, popularly known as metro rail, are likely to soar by a huge amount of money due mainly to some engineering conditions added by the Japanese donor...
www.newagebd.net
Costs of two MRT projects set to soar
Shahin Akhter 25 February, 2026, 23:59
Costs of two of the upcoming projects for the construction of mass rapid transit lines, popularly known as metro rail, are likely to soar by a huge amount of money due mainly to some engineering conditions added by the Japanese donor.
Expressing concerns, road transport sector experts said that these projects could lead the country to bankruptcy due to the burden of ‘illogical’ expenditures.
Officials of the Dhaka Mass Transit Company Limited, the implementing agency of the metro rail system, said that the government would make decision regarding the cost of these projects.
The work to build a network of about 141 kilometres of six MRT lines, comprising both elevated and underground ones, by 2030 started in 2016 in the Dhaka city to reduce traffic congestion and improve the environment in the capital and its suburbs.
Japan is providing loans for the construction of the first three MRT lines in Bangladesh through the Japan International Cooperation Agency.
Out of the six projects, metro trains are now running on the Uttara–Motijheel portion of the elevated 21.26 kilometres long MRT Line 6 project. The portion took about six years to be completed.
Works on its extension till Kamalapur are now going on while the project costs Tk 33,472 crore.
The 31.241-kilometre MRT Line 1, on the Hazrat Shahjalal International Airport-Kamalapur route, will be the first underground metro rail system in Bangladesh and its construction work started on February 2, 2023, while it was approved in December 2019.
For the MRT Line 1 project, the government estimated the cost at about Tk 52,500 crore with the deadline till December this year.
As per the contractors’ proposal, the estimated cost of the project reached about Tk 96,500 crore.
The construction of the 20-kilometre MRT Line 5’s Northern Route, on Hemayetpur-Bhatara route, started on November 4, 2023, with an estimated cost of Tk 41,200 crore and the December 2028 deadline.
For the project, approved in October 2019, as per the contractors’ proposal the estimated cost of the project now stands at about Tk 88,000 crore.
DMTCL managing director Faruque Ahmed said that the Japanese lending agency JICA had added several engineering conditions to the financing of the two projects.
As a result, competition in hiring contractors has decreased, he said, adding that this was one of the reasons why the current estimated costs were so high.
‘We do not know why the contractors are asking for so much cost,’ Faruque said, adding that now the government would make decision about the projects’ cost.
The managing director added that metro rail system was necessary for the capital while it was also important how cheaply a MRT line could be built instead of putting burden on people.
Professor Shamsul Hoque, who teaches civil engineering at the Bangladesh University of Engineering and Technology, said that there was a grave concern that these projects could lead the state to financial bankruptcy due to burden of ‘illogical’ expenditure.
Since the debt must be repaid in foreign currency, it places an immense pressure on the country and the people, especially as the Awami League government, which was ousted in August 2024 in the wake of a mass uprising, had already left behind a heavy debt load, said Shamsul, also an expert on transport engineering and road safety.
He also alleged that a syndicated tendering process where Japanese contractors and consultants dominated because the experience requirements were tailored to them, prevented competitive bidding, resulting in only a couple of contractors bidding for packages and then splitting the work.
Mentioning the routes of MRL line 1 and 5 (northern route), Shamsul further said that investing heavily in lines towards areas like Purbachal and Bhatara was ‘questionable’ because those areas were not yet fully inhabited.
‘This means the investment may never be recovered through fares, forcing the government into high subsidies,’ he observed.
The government should be visionary and consider international tenders rather than relying solely on one donor to ensure that public money is used for sustainable and cost-effective development, he added.
Shahin Akhter 25 February, 2026, 23:59
Costs of two of the upcoming projects for the construction of mass rapid transit lines, popularly known as metro rail, are likely to soar by a huge amount of money due mainly to some engineering conditions added by the Japanese donor.
Expressing concerns, road transport sector experts said that these projects could lead the country to bankruptcy due to the burden of ‘illogical’ expenditures.
Officials of the Dhaka Mass Transit Company Limited, the implementing agency of the metro rail system, said that the government would make decision regarding the cost of these projects.
The work to build a network of about 141 kilometres of six MRT lines, comprising both elevated and underground ones, by 2030 started in 2016 in the Dhaka city to reduce traffic congestion and improve the environment in the capital and its suburbs.
Japan is providing loans for the construction of the first three MRT lines in Bangladesh through the Japan International Cooperation Agency.
Out of the six projects, metro trains are now running on the Uttara–Motijheel portion of the elevated 21.26 kilometres long MRT Line 6 project. The portion took about six years to be completed.
Works on its extension till Kamalapur are now going on while the project costs Tk 33,472 crore.
The 31.241-kilometre MRT Line 1, on the Hazrat Shahjalal International Airport-Kamalapur route, will be the first underground metro rail system in Bangladesh and its construction work started on February 2, 2023, while it was approved in December 2019.
For the MRT Line 1 project, the government estimated the cost at about Tk 52,500 crore with the deadline till December this year.
As per the contractors’ proposal, the estimated cost of the project reached about Tk 96,500 crore.
The construction of the 20-kilometre MRT Line 5’s Northern Route, on Hemayetpur-Bhatara route, started on November 4, 2023, with an estimated cost of Tk 41,200 crore and the December 2028 deadline.
For the project, approved in October 2019, as per the contractors’ proposal the estimated cost of the project now stands at about Tk 88,000 crore.
DMTCL managing director Faruque Ahmed said that the Japanese lending agency JICA had added several engineering conditions to the financing of the two projects.
As a result, competition in hiring contractors has decreased, he said, adding that this was one of the reasons why the current estimated costs were so high.
‘We do not know why the contractors are asking for so much cost,’ Faruque said, adding that now the government would make decision about the projects’ cost.
The managing director added that metro rail system was necessary for the capital while it was also important how cheaply a MRT line could be built instead of putting burden on people.
Professor Shamsul Hoque, who teaches civil engineering at the Bangladesh University of Engineering and Technology, said that there was a grave concern that these projects could lead the state to financial bankruptcy due to burden of ‘illogical’ expenditure.
Since the debt must be repaid in foreign currency, it places an immense pressure on the country and the people, especially as the Awami League government, which was ousted in August 2024 in the wake of a mass uprising, had already left behind a heavy debt load, said Shamsul, also an expert on transport engineering and road safety.
He also alleged that a syndicated tendering process where Japanese contractors and consultants dominated because the experience requirements were tailored to them, prevented competitive bidding, resulting in only a couple of contractors bidding for packages and then splitting the work.
Mentioning the routes of MRL line 1 and 5 (northern route), Shamsul further said that investing heavily in lines towards areas like Purbachal and Bhatara was ‘questionable’ because those areas were not yet fully inhabited.
‘This means the investment may never be recovered through fares, forcing the government into high subsidies,’ he observed.
The government should be visionary and consider international tenders rather than relying solely on one donor to ensure that public money is used for sustainable and cost-effective development, he added.