โ˜• Support Us โ˜•
[๐Ÿ‡ง๐Ÿ‡ฉ] - Energy Security of Bangladesh | Page 41 | PKDefense

[๐Ÿ‡ง๐Ÿ‡ฉ] Energy Security of Bangladesh

Reply (Scroll)
Press space to scroll through posts
G Bangladesh Defense
[๐Ÿ‡ง๐Ÿ‡ฉ] Energy Security of Bangladesh
480
15K
More threads by Saif


Power sector managers need to ensure quality control
01 May, 2025, 00:00

THE absence of a quality control mechanism in the power sector has led to extra fuel costs in power generation. A recent Power Development Board analysis shows that some plants consume up to 90 per cent more fuel than others do. The finding indicates an overall power management failure in stopping the leak of the already scanty supplies of imported fuels. Experts say that factors such as the import and transport cost, the dollar exchange rate, plant factor and, especially, the quality of machines that contribute to varying degrees of fuel consumption, exist in the power sector. During the Awami League regime, when the power sector experienced a lopsided development, driven by an abnormally high overcapacity and an absurd capacity charge system, many party loyalists were rewarded with power projects without tender under the now-repealed indemnity law, with the power sector investors choosing their machines while quality control mechanisms did not exist. Independent power plants exploited the situation and brought used machines that led to the over-consumption of fuels and frequent shutdown of plants. The public power plants also used more fuels as they were poorly maintained. The scenario has not yet changed.

The frequent shutdowns of power plants, not only the old ones but also new ones, because of technical glitches show the absence of quality checks. For example, the first unit of the 1,320MW coal-fired Rampal plant, a Bangladesh-India joint venture, shut down eight times in the first nine months after it started running in December 2022. The plant, where per-unit fuel cost is 28 per cent higher than a similar power plant, was available for only 18 per cent of the time this January, according to the power board. Frequent shutdowns and resumptions of the plants require extra fuel. The fuel cost in the Tongi Power Plant is 47 per cent higher compared with the average cost of fuel in similar plants. Many other plants have continued to operate at a little fraction of their capacity. Among gas-based plants, as the power board analysis shows, the average fuel costs of public plants are about 20 per cent higher than that of independent power plants, largely because of old machines that have served out their economic life. So is the case with oil- and coal-based public power plants. Some independent power plants, including Adani and Summitโ€™s, also have high fuel costs riding on unequal power deals.​
 

Bangladesh substantially reduces its outstanding dues to Adani
Dilip Jha, chief financial officer of the India-based company, tells Reuters
FE ONLINE DESK
Published :
May 02, 2025 18:13
Updated :
May 02, 2025 18:17

1746232814685.png


Bangladesh has substantially reduced its outstanding dues to India's Adani Power related to a power-supply deal, and the company is confident of recovering the roughly $900 million still remaining, its chief financial officer said.

According to Reuters, Bangladesh has struggled to pay its dues per the deal, signed in 2017, as imports got costly since the Russia-Ukraine conflict in 2022 and amid the domestic political turmoil last August that led to the ouster of the country's prime minister.

As a result, Adani had halved supply last year but CFO Dilip Jha said the company has resumed full supply since as the country's monthly payments started covering some of the dues.

"We are supplying full power to Bangladesh ... the payment we are receiving now is more than the monthly billing," Jha said in a post-earnings call with analysts on Thursday.

"We are hopeful that not only will we continue to receive payments equivalent to the current month's billing, but that the old outstanding dues will also be liquidated."

The company said Bangladesh has paid nearly $1.2 billion of the roughly $2 billion totally billed to the country.​
 

Gas crisis in industries as supply increased in power sector
The supply of gas is lower than the demand. On top of that supply of gas to the power plants has been increased to cut down on load shedding.

Mohiuddin Dhaka
Published: 29 Apr 2025, 08: 41

1746236775946.png

Machineries at a dye factory remain idle due to gas crisis. Photo taken in BCIC Industrial Estate in Fatullah, Narayanganj. Prothom Alo

The demand for electricity is at its highest during summer. When production of electricity cannot meet the demand, there has to be power load shedding. The government this time, however, has been trying to limit the load shedding.

So, the electricity generation has been increased to keep the supply of electricity uninterrupted. To maintain this production, the supply of gas has been increased in the electricity sector, cutting down on the supply of that to the industrial and residential sectors.

Bangladesh Oil, Gas and Mineral Corporation (Petrobangla) sources say that the daily demand of gas in the country stands at 3.8 billion (380 crore) cubic feet. The demand can somewhat be met when thereโ€™s a supply of 3 billion (300 crore) cubic feet. Then the situation is managed by rationing (by reducing the supply in one sector and increasing in another).

At present there is a supply of 2.7 billion (270 crore) cubic feet. Of that, 1.05 billion (105 crore) cubic feet is being supplied to the power plants.

The power sector is now considered with highest priority. As a result, the gas crisis has widened for the residential and industrial clients.

The largest gas distribution company, Titas Gas Transmission and Distribution, supplies gas to Dhaka, Gazipur, Mymensingh and Narayanganj regions.

Officials of this company say that their daily demand is 1.9 billion (190 crore) cubic feet. Currently, they are receiving about 1.52 to 1.53 billion (152 to 153 crore) cubic feet.

During times of such supply before, they could provide a maximum of 230 million (23 crore) cubic feet to the power sector. Now they have to provide 360 to 370 million (36 to 37 crore) cubic feet in this sector. This has created a shortage of 130 to 140 million (13 to 14 crore) cubic feet in the industrial and residential sectors. There is a shortage of gas in the industry even during the normal times. Now it has increased even more.

Even though the industrial customers pay higher prices, the power sector has to be prioritised in gas supply. Two more cargoes of LNG ships would have to be imported to meet the demand.
Director of operations and mines at the Petrobangla, Md Rafiqul Islam told Prothom Alo that the supply of gas to the power sector has been increased and this has created a bit of shortage. Local gas production might increase a bit within a day or two.

The idea of increasing LNG (Liquefied Natural Gas) import is also being pondered upon, he added.

The country once produced 2.7 billion (270 crore) cubic feet of gas every day. Then the LNG import started in 2018 when the production started declining. The daily production has now dropped to 1.84 billion (184 crore) cubic feet.

Though the LNG import has increased than before, it is still not sufficient. About 800 to 850 million (80 to 85 crore) cubic feet of gas is supplied daily from the imported LNG.

A Petrobangla official stated that the company earns Tk 22.87 from selling per unit of gas while they are now spending an average of more than Tk 27 on the same unit.

Although gas is sold to the industry sector for Tk 30 per unit, the price of gas in the power sector is Tk 14.75.

Even though the industrial customers pay higher prices, the power sector has to be prioritised in gas supply. Two more cargoes of LNG ships would have to be imported to meet the demand.

This will increase the amount of losses for Petrobangla. However, more cargoes can be imported if the Power Development Board (PDB) pays a price of Tk 27.

Narayanganj and Gazipur, the two districts next to Dhaka, are mainly known as industrial zones. Most of the export-oriented readymade garment factories are located here. Production in these factories has been disrupted for a long time due to the gas crisis. It has turned even worse in the last two weeks.

Manager (transmission and distribution) of Titas Gas in Gazipur Md Redwan told Prothom Alo that the demand of gas in Gazipur stands now at 600 million (60 crore) cubic feet but only 350 million (35 crore) cubic feet is supplied.

According to industrial police data, there are a total of 2,176 factories in Gazipur district. Out of them, 1,187 are garment factories.

The number of small and large factories there would increase to about 5,000 if the unlicensed ones are counted in. Most of these factories are gas-powered.

Sohel Rana, Director of Sadma Group located in Mouchak area of Gazipur, told Prothom Alo that the gas pressure needs to be between 10 to 15 PSI (pound per square inch) for the factory to be running. But, there has not been more than two to three PSI of gas pressure in the last 15 days. Our production has been slashed by 30 to 40 per cent from this.

Deputy General Manager at Titas Gasโ€™ Narayanganj office, Mamunur Rashid told Prothom Alo that the industrial and residential clients are receiving less amount of gas in some parts due to low supply.

MS Dyeing Printing and Finishing Limited, situated in BSCIC Industrial Estate in Fatullah of Narayanganj, has a production capacity of 40 tonnes. However, their production has dropped to 10 tonnes.

The company sent a letter to Titas on 23 April mentioning the matter of commercial losses caused from the low gas pressure.

While visiting the factory Sunday afternoon, the boiler was found shut and the gas pressure reading showed zero PSI. Another factory in BSCIC Industrial Estate, Fare Apparels Limited was out of production since morning and the workers were found sitting idle.

Research director at non-government research organisation, Centre for Policy Dialogue (CPD), Khondaker Golam Moazzem told Prothom Alo that managing the energy supply crisis is a major challenge for the government.

They have to take the social, economic and political aspects into consideration, he advised.

According to him, the government must not go for increased LNG import to strike a balance in gas supply. โ€œWe need to emphasise on exploring and producing gas domestically.โ€

[Prothom Alo correspondents in Gazipur and Narayanganj have helped prepare this report.]

* The report, originally published in the print and online edition of Prothom Alo, has been rewritten in English by Nourin Ahmed Monisha​
 

Matarbari power as expensive as peers
Tariff could exceed Tk 13 a unit
Emran Hossain 03 May, 2025, 00:45

1746237085675.png


The power tariff of the coal-fired 1,200-megawatt Matarbari power plant is going to be as high as its peers, observed energy experts, saying that the government-approved power tariff made it appear as if the tariff was lower than that of the electricity purchased from similar power plants.

On April 29, the advisory committee on government purchase approved the public power plantโ€™s power tariff at Tk 8.44 a kilowatt-hour or 7.6621 US cents a kWh, with Tk 5.84 a kWh spent as fuel cost and Tk 2.60 a kWh given as capacity charge.

An official document showed that the rates of fuel use and capacity charge were determined considering that the power plant operated at 85 per cent of its capacity.

The document also showed that the calculation considered the dollar exchange rate to be Tk 110.25.

The dollar exchange rate is crucial in determining the tariff since power plants depend on fuel import for their production and their capacity charge is paid mostly in the dollar. The current dollar rate, according to the Bangladesh Bank, is Tk 122.

โ€˜Considering the dollar rate at such a low level in the calculation is misleading,โ€™ said Hasan Mehedi, member secretary of the Bangladesh Working Group on Ecology and Development, a forum of rights activists and organisations.

โ€˜The tariff of coal-based power plant is tough to determine for it involves so many issues and uncertainties,โ€™ he said.

An analysis done past year by the Bangladesh Power Development Board revealed that the average fuel cost among all coal-fired power plants in the country was Tk 7.02, more than 16 per cent higher than what the newly approved Matarbari tariff allowed.

The fuel cost varied greatly depending mainly on machine quality, coal quality and the operational period of power plants. For instance, the fuel cost in a unit of the Barapukuriya power plant was Tk 12.30, the PDB analysis showed.

In joint venture coal-based power plants, the fuel cost ranged between Tk 6.67 and Tk 7.84. The coal-fired independent power plantsโ€™ fuel cost ranged between Tk 6.26 and Tk 6.75.

For an ultra-supercritical coal power plant, the technology of which is also used in Matarbari, the BPDBโ€™s fuel cost stood at Tk 6.77.

The fuel cost could vary greatly due to the high vulnerability of the international fuel market. During the Covid pandemic, the price of a tonne of coal reached $400. The current price of coal is below $100 a tonne.

The BPDB analysis also revealed that the average government-set cost stood at Tk 4.63 past year, nearly 45 per cent higher than what the Matarbari was allowed to get.

โ€˜The plant availability factor could influence the power tariff,โ€™ said Shafiqul Alam, lead energy analyst at the Institute for Energy Economics and Financial Analysis, a research organisation.

Power tariff goes up if the plantโ€™s capacity remains unutilised, energy analysts said, given that the capacity charge is paid anyway. Increased utilisation contributes greatly to decreasing tariff, they said.

In 2023-24, according to the BPDB, the average plant availability among the coal-based power plants was 35.25 per cent.

The plant factor of the Adani coal power plant, which is supplying electricity from India, was 62.32 per cent, which was the second highest plant factor after import with 85 per cent plant factor.

Power plants in Bangladesh have never run at 85 per cent of their capacity in recent time.

The ongoing dollar crisis is a major reason for keeping power plants idle due to lack of fuel supply.

The BWGED estimated that the Matarbari power plant would actually get Tk 2,565 crore a year at the current dollar exchange rate.

If the plant availability dropped to 60 per cent, the BWGED said that at the newly announced tariff per unit of production cost at the Matarbari power plant would stand at Tk 10.55.

The tariff would increase to Tk 13.14 if the plant availability dropped to 37 per cent, which was the average plant availability of Barapukuria and Payra power plants between the financial years of 2020-21 and 2023-24.

The average coal power tariff in 2023-24 was Tk 12.74.

ANM Obaidullah, member of the BPDB, said that the government-approved tariff was determined based on the dollar exchange rate the day the plant rolled into commercial operation.

โ€˜This is the base price,โ€™ said Obaidullah.

โ€˜Depending on situations, the tariff could be changed,โ€™ he said, saying that power tariffs were paid after evaluation based on the actual situation.

Unlike the other power plants, the Matarbari power plant started its operation without having signed a power purchase agreement.

The first unit of the Matarbari power plant started commercial operation in December 2023 and the second unit started operation in August 2024.

So far the plant has received only the fuel cost for running its operation.​
 

Bangladesh to buy six spot LNG cargoes in May
FE ONLINE REPORT
Published :
May 03, 2025 19:11
Updated :
May 03, 2025 19:11

1746317535957.png


The government is eyeing importing a total of six spot liquefied natural gas (LNG) cargoes in May, the highest number in a single month, to meet mounting summer demand.

State-run Rupantarita Prakritik Gas Company Ltd (RPGCL) already bought five spot LNG cargoes for May delivery windows, a senior RPGCL official told The Financial Express on Saturday.

He said the RPGCLโ€™s tender to buy one more spot LNG cargo in the May 30-31 delivery window is also open, along with two more spot LNG cargo tenders for the June 26-27 and July 2-3 delivery windows.

The countryโ€™s energy demand has gone up since early April with the advent of summer, which is expected to grow further with the rise of mercury.

Bangladesh bought four spot LNG cargoes for the deliveries in the past two months โ€“ March and April.

The bid winners will deliver the LNG cargoes at Moheshkhali Island in the Bay of Bengal, with options to discharge the cargo at either of the countryโ€™s two floating storage regasification units (FSRUs) located on Moheshkhali Island.

The RPGCL, a wholly owned subsidiary of state-run Bangladesh Oil, Gas, and Mineral Corporation, or Petrobangla, looks into LNG trades in Bangladesh.

The volume of each of the spot LNG cargoes will also be around 3.36 million British thermal units (MMBtu).

Bangladesh previously awarded its latest spot LNG cargo to Gunvor Singapore Pte Ltd. for the May 25-26 delivery window at $11.83 per MMBtu.

Bangladesh currently imports LNG from Qatar Energy and OQ Trading International under long-term deals and purchases LNG also from the spot market to re-gasify LNG in its two operational FSRUs, having a total capacity of 1.10 billion cubic feet per day (Bcfd).

The country has been reeling from an acute energy crisis as its natural gas output is depleting.

Bangladesh has been rationing gas supply to industries, power plants and other gas-guzzling industries to cope with the mounting demand.​
 

Tackling renewable energy's critical dimensions
Muhammad Zamir
Published :
May 04, 2025 23:53
Updated :
May 04, 2025 23:53

1746404865592.png


Renewable energy, also called green energy, is made from renewable natural resources that are replenished on a human timescale. Some also consider nuclear power a renewable power source, although this is controversial, as nuclear energy requires mining uranium, a nonrenewable resource. Renewable energy installations can be large or small and are suited for both urban and rural areas.

Renewable energy systems have rapidly become more efficient and cheaper over the past 30 years. A large majority of worldwide newly installed electricity capacity is now renewable. Renewable energy sources, such as solar and wind power, have seen significant cost reductions over the past decade, making them more competitive with traditional fossil fuels. From 2011 to 2021, renewable energy has grown from 20 per cent to 28 per cent of global electricity supply. Power from the Sun and wind accounts for most of this increase, growing from a combined 2 per cent to 10 per cent. Use of fossil energy has also shrunk from 68 per cent to 62 per cent. In 2024, renewables accounted for over 30 per cent of global electricity generation and are projected to reach over 45 per cent by 2030. Many countries already have renewables contributing more than 20 per cent to their total energy supply, with some generating over half or even all their electricity from renewable sources.

Renewable energy is usually understood as energy harnessed from continuously occurring natural phenomena. The International Energy Agency defines it as "energy derived from natural processes that are replenished at a faster rate than they are consumed". Solar power, wind power, hydroelectricity, geothermal energy and biomass are widely agreed to be the main types of renewable energy. Renewable energy often displaces conventional fuels in three particular areas-- electricity generation, heating water and transportation. It is also useful for providing rural (off-grid) energy services.

Solar power produced around 1.3 terrawatt-hours (TWh) worldwide in 2022, representing 4.6 per cent of the world's electricity. Almost all of this growth has happened since 2010. Solar energy can be harnessed anywhere that receives sunlight; however, the amount of solar energy that can be harnessed for electricity generation is influenced by weather conditions, geographic location and time of day.

At this point one also needs to recognise that renewable energy has a critical role in addressing climate change. As part of the global effort to limit climate change, most countries have committed to net-zero greenhouse gas emissions. In practice, this means phasing out fossil fuels and replacing them with low-emissions energy sources. This much needed process, coined as "low-carbon substitutions" in contrast to other transition processes including energy additions, needs to be accelerated multiple times in order to successfully mitigate climate change. It may be recalled that at the 2023 United Nations Climate Change Conference, around three-quarters of the world's countries set a goal of tripling renewable energy capacity by 2030.

The European Union aims to generate 40 per cent of its electricity from renewables by the same year. The European Union has pledged Euro 1.3 billion, urging Bangladesh to increase renewable energy use by over 3 per cent and reform its energy structure. Recently, an event--"Renewable Energy Fest 2025" in Bangladesh focused on a green energy transition through policy reform, innovation and youth participation. Dr. Michal Krejza of the EU Delegation in Bangladesh, emphasised regional energy connectivity and said, "The EU has pledged Euro 1.3 billion to increase Bangladesh's renewable energy use by more than 3 per cent and reform its energy structure. This is being considered as vital if Bangladesh is to reach its electricity demand of 58,410 MW by 2041.

It would be pertinent to understand that renewable energy is more evenly distributed around the world than fossil fuels, which are concentrated in a limited number of countries. It also brings health benefits by reducing air pollution caused by the burning of fossil fuels.

Solar power produced around 1.3 terawatt-hours (TWh) worldwide in 2022, representing 4.6 per cent of the world's electricity. Almost all of this growth has happened since 2010. Solar energy can be harnessed anywhere that receives sunlight; however, the amount of solar energy that can be harnessed for electricity generation is influenced by weather conditions, geographic location and time of day.

Eco-scientists have observed that humans have harnessed wind energy for more than 2200 years. Until the 20th century, it was primarily used to power ships, windmills and water pumps. Today, the vast majority of wind power is used to generate electricity using wind turbines. Modern utility-scale wind turbines range from around 600 kW to 9 MW of rated power. The power available from the wind is a function of the cube of the wind speed, so as wind speed increases, power output increases up to the maximum output for the particular turbine. Areas where winds are stronger and more constant, such as offshore and high-altitude sites, are preferred locations for wind farms.

Wind-generated electricity met nearly 4 per cent of global electricity demand in 2015, with nearly 63 GW of new wind power capacity installed. Wind energy was the leading source of new capacity in Europe, the US and Canada, and the second largest in China. In Denmark, wind energy met more than 40 per cent of its electricity demand while Ireland, Portugal and Spain each met nearly 20 per cent.

Globally, the long-term technical potential of wind energy is believed to be five times total current global energy production, or 40 times current electricity demand, assuming all practical barriers needed were overcome. This would require wind turbines to be installed over large areas, particularly in areas of higher wind resources, such as offshore and likely also industrial use of new types of VAWT turbines in addition to the horizontal axis units currently in use. As offshore wind speeds average ~90 per cent greater than that of land, offshore resources can contribute substantially more energy than land-stationed turbines.

Investments in wind technologies reached US Dollar 161 billion in 2020, with onshore wind dominating at 80 per cent of total investments from 2013 to 2022. Offshore wind investments nearly doubled to US Dollar 41 billion between 2019 and 2020, primarily due to policy incentives in China and expansion in Europe.

It needs to be noted here that technological research is continuing at a serious and comprehensive manner with regard to the improvement of renewable energy technologies. There are also other renewable energy technologies that are still under development, including enhanced geothermal systems, concentrated solar power, cellulosic ethanol and marine energy.

The International Renewable Energy Agency (IRENA) has stated that ~86 per cent (187 GW) of renewable capacity added in 2022 had lower costs than electricity generated from fossil fuels. IRENA also stated that the capacity added since 2000 reduced electricity bills in 2022 by at least US Dollar 520 billion, and that in non-OECD countries, the lifetime savings of 2022 capacity additions will reduce costs by up to US Dollar 580 billion.

Solar power, also known as solar electricity, is the conversion of energy from sunlight into electricity, either directly using photovoltaics (PV) or indirectly using concentrated solar power. Solar panels use the photovoltaic effect to convert light into an electric current. Concentrated solar power systems use lenses or mirrors and solar tracking systems to focus a large area of sunlight to a hot spot, often to drive a steam turbine.

Photovoltaics (PV) were initially solely used as a source of electricity for small and medium-sized applications, from the calculator powered by a single solar cell to remote homes powered by an off-grid rooftop PV system. Commercial concentrated solar power plants were first developed in the 1980s. Since then, as the cost of solar panels has fallen, grid-connected solar PV systems' capacity and production has doubled about every three years. Three-quarters of new generation capacity is solar, with both millions of rooftop installations and gigawatt-scale photovoltaic power stations continuing to be built.

By 2024, solar power was generating 6.9 per cent (2,132 TWh) of global electricity and over 1 per cent of primary energy, adding twice as much new electricity as coal. Along with onshore wind power, utility-scale solar has become the source for new installations in most countries. As of 2023, 33 countries generated more than a tenth of their electricity from solar, with China making up more than half of solar growth. Almost half the solar power installed in 2022 was mounted on rooftops.

It would be worthwhile to point out here that solar-cell efficiencies of laboratory-scale devices using pertinent materials have increased from 3.8 per cent in 2009 to 25.7 per cent in 2021 in single-junction architectures, and, in silicon-based tandem cells, to 29.8 per cent, exceeding the maximum efficiency achieved in single-junction silicon solar cells. Perovskite solar cells have, therefore, been the fastest advancing solar technology as of 2016. With the potential of achieving even higher efficiencies and very low production costs, perovskite solar cells have become commercially attractive. Core problems and research subjects include their short and long-term stability.

Recently experts have suggested that Bangladesh urgently needs a long-term financing roadmap to promote renewable-energy projects and reach the country's target of net-zero carbon emission by 2050. They have also observed that to achieve the goal, the country that is extremely vulnerable to global warming, also requires the framing of the monetary policy in such a way that the commercial lenders-- both state-owned commercial Banks (SCBs) and private commercial Banks (PCBs)-- can feel encouraged to support proliferation of renewable energy.

In this context, it was good to know that the Islamic Development Bank (IsDB) has agreed to provide US Dollar 167 million in loans -- roughly Tk 20.10 billion -- to develop a 220MW solar power plant in the Sonagazi area of Feni district, a facility with the highest solar capacity in the country to date. The Power Division proposed the project with an estimated cost of Tk 21.35 billion, with the combined contribution of the government and Electricity Generation Company of Bangladesh Limited (EGCB) amounting to Tk 1.25 billion, according to Planning Commission sources. The project seeks to reduce dependence on fossil fuels, lower carbon emissions, and contribute to economic development and improved living standards.

Muhammad Zamir, a former Ambassador, is an analyst specialised in foreign affairs, right to information and good governance.​
 

Govt to buy 4 more LNG cargoes over next 4 months to supply more gas to industries
FE Online Report
Published :
May 07, 2025 20:14
Updated :
May 07, 2025 20:14

1746664074126.png


The government has moved to buy four additional liquefied natural gas (LNG) cargoes during the next four months from May to August at the cost of around Tk 28 billion to allocate more gas to industrial consumers.

State-run Petrobangla will also reduce natural gas allocations for gas-fired power plants to 1,050 million cubic feet per day (mmcfd) from existing 1,200 mmcfd to ramp up gas supply to industries by 150 mmcfd.

Adviser of the Ministry of Power, Energy and Mineral Resources Muhammad Fouzul Kabir Khan drew up the plan to ramp up natural gas supplies to industries during a meeting with businesspersons at the Secretariat Wednesday.

Some 100 mmcfd of additional gas from additional LNG cargoes and some 150 mmcfd from divertion will ensure around 250 mmcfd of additional gas in total for industries during the next four months, said Mr Khan.

The government will have to spend an additional Tk110 billion to supply this additional gas to the industry, he added.

President of Bangladesh Knitwear Manufacturers and Exportersโ€™ Association (BKMEA) Md Hatem, Hamim Group Director AK Azad, Meghna Group managing director Mostafa Kamal, Pran Group Chairman Ahsan Khan Chowdhury, Bangladesh Chamber of Industries (BCI) president Anwar Ul Alam Chowdhury Parvez, energy secretary Saiful Islam, Petrolbangla Chairman Md Rezanur Rahman and Chief Advisor's press secretary Shafiqul Alam were among others attended the meeting.​
 

Govt floats tender to buy one more spot LNG cargo in June
FE Online Report
Published :
May 11, 2025 19:20
Updated :
May 11, 2025 19:31

1747007812858.png


The government has reissued a tender to purchase one spot LNG cargo for the June 26โ€“27 delivery window to meet growing summer demand from industries and power plants.

State-run Rupantarita Prakritik Gas Company Ltd (RPGCL) reissued the tender last week to procure the cargo, which will have a volume of around 3.36 million British thermal units (MMBtu).

The winning bidder will deliver the LNG cargo to Moheshkhali Island in the Bay of Bengal, with the option to discharge it at either of the countryโ€™s two floating storage and regasification units (FSRUs) located on the island.

RPGCL reissued the tender after cancelling the previous one because of receiving higher-than-expected price proposals from suppliers, said a senior RPGCL official.

If this tender succeeds, the countryโ€™s total spot LNG purchases for June will be three cargoes -- half the number purchased in May, he said.

Bangladesh bought six spot LNG cargoes for May deliveries, the highest in a single month so far this year.

The country expects lower LNG demand in June due to cooler temperatures and monsoon rainfall, which is likely to result in fewer spot LNG purchases, the RPGCL official added.

RPGCL, a wholly owned subsidiary of state-run Petrobangla, oversees LNG trading in Bangladesh.

Recently, Bangladesh awarded two spot LNG cargo tenders to Vitol Asia Pte Ltd for the May 30โ€“31 and July 2โ€“3 delivery windows at \$11.44 per MMBtu and \$11.57 per MMBtu, respectively.

In addition to spot cargoes, Bangladesh has been importing LNG from its two long-term suppliers --QatarEnergy LNG (formerly Qatargas) and OQ Trading International -- for regasification at its two operational FSRUs.​
 

Wattโ€™s going on? A renewable dream stuck in load-shedding

1747011232937.png

Renewable Energy Policy (REP) 2025 needs a serious rewrite. Targets must be based on sound projections, not fantasies. FILE ILLUSTRATION: REHNUMA PROSHOON

Renewable energy in Bangladesh is a bit like your overly ambitious cousin who swears they'll start waking up at 6:00 am, run 10 kilometres, and read Tolstoy before breakfastโ€”grand promises, minimal follow-through, and inevitably back to square one by the weekend. Every now and then, we're treated to a flashy announcement: a new solar megaproject here, a bold wind energy target there, all wrapped in glossy government statements and hashtags like #GreenBangladesh. We are now in 2025, and despite years of courtship with solar panels and flirtation with wind turbines, we're still stuck in a toxic relationship with fossil fuelsโ€”cuddling up to imported coal and whispering sweet nothings to liquefied natural gas (LNG).

Let's look at the reality behind the ribbon cuttings. Despite years of lofty commitments and climate conference pledges, renewable energy in Bangladesh accounts for only about 4.5 percent of total installed capacity, and more than 80 percent of that comes from solar. But even that number flatters to deceive. Most of it is from small, decentralised systemsโ€”rooftop solar, solar home systems in villagesโ€”not large-scale, grid-connected solar farms. The sun might shine relentlessly here, but our solar energy ambitions collapse faster than a flimsy Dhaka umbrella in July rain.

Why is the picture so bleak in a country that quite literally bakes under the sun and gets enough wind along the coast to power an Atif Aslam concert? Because our approach to renewable energy is equal parts chaotic and comical. Think of it as a gym subscription, enthusiastically bought, barely used, and always waiting for "the first of next month." One minute we're promising 6,000 megawatts of renewable energy by 2025, and the next, we're cutting the power sector budget by 15 percent and quietly stalling the very policy reforms that would make those targets remotely achievable.

Let's dissect the big announcement. The long-awaited draft of the Renewable Energy Policy (REP) 2025 was finally published in February, heralding the same old excitement, now with bigger numbers. It promises that by 2030, Bangladesh will generate 20 percent of its electricityโ€”6,145 megawattsโ€”from renewables. By 2041, this will leap to 30 percent. It sounds impressive until you realise the whole projection is based on an inflated electricity demand estimate from the Integrated Energy and Power Master Plan (IEPMP). According to the Centre for Policy Dialogue (CPD), a more realistic figure for 20 percent renewable electricity by 2030 would be around 5,600 megawatts, and just 10,500 megawatts for 30 percent by 2041. In other words, the government has taken some creative liberties with its math.

Let's not forget that back in 2008, Bangladesh set a modest goal of reaching 10 percent renewable electricity by 2020. That deadline ghosted us like a flaky Hinge match. Fast forward to today, and we're barely scraping five percent. Yet we are now expected to believe we'll quadruple that number in just six years. To put things in perspective, even China, the undisputed heavyweight champion of renewables, is targeting 25 percent non-fossil energy by 2030. Bangladesh, which has neither China's resources, infrastructure, nor investment climate, thinks it can match that. Bold. Delusional, but bold.

What really makes the draft policy shine, in the same way cheap plastic does under bad lighting, is its complete avoidance of any fossil fuel phase-out plan. Countries like the United Kingdom and Germany have legally committed to phasing out coal. Bangladesh? We're still busy signing new fossil fuel deals like it's 1999. The draft throws around the phrase "green energy" with such abandon you'd think it means anything remotely not-blackโ€”bioenergy, waste-to-energy, and other vaguely greenish things. Meanwhile, natural gas and nuclear power continue to dominate the IEPMP, making the entire renewable section of the policy feel like a reluctant afterthought, written at 2:00am before a donor meeting.

It gets betterโ€”or worse, depending on your appetite for bureaucratic chaos. The draft assigns oversight of renewable energy projects to the Sustainable and Renewable Energy Development Authority (SREDA ), while giving licensing power to the Bangladesh Energy Regulatory Commission. So now, we're left with a classic two-headed administrative monster. One body to dream up ideas, another to sign them off, and both to blame each other when nothing gets done.

Financing? That part is written in invisible ink. The policy mumbles about a Sustainable Energy Development Fund but uses delightful hedging language like "may be implemented" and "could be considered." Which is a bit like a marriage proposal that goes, "I might, perhaps, love youโ€ฆ in theory." It name-drops Bangladesh Bank and the Infrastructure Development Company Limited but forgets to outline how any of this will translate into real money. There's not a single concrete strategy to generate the billions of dollars necessary for this transition. And foreign investors? The policy greets them with all the warmth of a Dhaka traffic jam. No incentives, no guarantees, just a polite shrug and a vague mention of possible stamp duty waivers.

Industries, which consume most of the electricity in the country, don't fare much better. The draft policy gives a casual nod to rooftop solar for factories but offers no real blueprint for integrating solar energy into the energy-hungry manufacturing sector. It dangles carrots like "production-linked incentives may be provided" and "waivers may be considered for EVs," without saying anything. The entire policy reads like a horoscopeโ€”generously vague, suspiciously optimistic, and completely open to interpretation.

And what of our national grid? Ah, yes, that antique piece of electrical infrastructure, about as ready for a renewable revolution as a tea kettle is for launching satellites. Our solar projects sit idle because the grid can't handle the load. Wind projects are stuck in limbo. Meanwhile, someone from the ministry insists it was all "working fine yesterday."

Meanwhile, ministers cruise around in fossil-fuel-guzzling sports utility vehicles (SUVs), giving speeches about green energy in front of billboards that read "Go Green" in fonts large enough to be visible from outer space. It's satire that writes itself.

So, what can actually be done? For starters, REP 2025 needs a serious rewrite. Targets must be based on sound projections, not fantasies. A proper fossil fuel phase-out timeline must be included. Financial incentives should be made real, not theoretical. Off-grid and rooftop solar should be given a central role in industrial zones. SREDA needs to be empowered with full licensing authority, so at least someone is clearly in charge. And above all, we need to swap out all those "may"s and "could"s for "shall"s and "will"sโ€”because climate change doesn't respond to passive voice.

Right now, Bangladesh's renewable energy policy looks like it was written to impress donors and confuse citizens. And as we fumble forward with candles during load-shedding, fanning ourselves with expired optimism, it's worth remembering potential means nothing without action.

Thus, here's hoping we graduate from glossy dreams to gritty implementation. Because sunlight may be free, but stupidity is proving to be very, very expensive.

Barrister Noshin Nawal is an activist, feminist, and a columnist for The Daily Star.​
 

Govt set to nearly halve power subsidies in FY 2026
FHM Humayan Kabir
Published :
May 14, 2025 00:55
Updated :
May 14, 2025 00:55

1747180534559.png


The government is set to halve the power subsidy for the next fiscal year (FY2025-26) to reduce the financial burden on the exchequer.

A substantial payment already made to clear the outstanding bills accumulated over the last couple of years for purchasing electricity from the independent power producers and an efficient power-sector- management plan apparently helped the government to go for the cutback.

Analysts, however, suggested maintaining a balance between the subsidy reduction and electricity tariffs so that the consumers, particularly households, do not have to bear the brunt.

In the national budget for FY 2025-26, scheduled to be placed in parliament on June 2, the allocation for power subsidy would be Tk 350 billion, about 56.5 per cent of Tk 620 billion revised allocation for the outgoing fiscal year, officials said on Tuesday.

The original allocation for power subsidy was Tk 360 billion for FY 2024-25.

The plan to cut Tk 270 billion or nearly 43.5 per cent signals a major shift in the government's approach to managing the financial burden of the power sector, analysts said.

The current fiscal year witnessed a considerable increase in power subsidies due to huge payment obligations of outstanding bills, accumulated over the last couple of years on account of mainly capacity charges and other bills of power producers.

"We have a plan to cut the subsidy in the upcoming FY as we have already paid a major portion of the dues in the current FY," said a senior official at the Ministry of Finance (MoF).

He said the power sector is likely to get an allocation of Tk 350 billion as the subsidy aimed at paying the arrears and bills of the Independent Power Producers (IPPs) like Indian Adani Power, Summit Power, and Aggreko Intl.

Bangladesh needs to provide huge subsidies every year mainly to pay outstanding bills to the IPPs against the purchase of electricity at higher rate from the producers and sell it to the consumers at lower prices.

An MoF official told the FE that they had already released Tk 460 billion out of Tk 620 billion subsidies, kept aside at the revised national budget for FY2025, to pay the arrears.

The remaining amount of subsidies would be released based on the demand by the Bangladesh Power Development Board (BPDB) in the coming days, he added.

The interim government augmented budgetary subsidy to Tk 620 billion in the current FY2025 budget as it wishes to pay the accumulated arrears by the next fiscal year.

The government owed the IPPs and the private-sector rental- power plants nearly Tk 130 billion until last month (April), as per data collected by the FE from the Power Division and the MoF documents on the payment obligations.

Indian Adani Power, Bangladesh-China Power Company Plant (Payra power plant), Meghnaghat 450MW Power Ltd, 210MW Rural Power Co Ltd, 335MW Summit-Meghnaghat Power Ltd and 414MW Sembcorp NWPC Ltd, 145MW Aggreko International Projects, United Power and Doreen Power are the major IPPs working in Bangladesh.

Another MoF official said that they are going to allocate a comparatively lesser amount of funds for the next FY as the power subsidy in the upcoming national budget amid expectations of a potential easing of global fuel prices in the coming fiscal year.

Moreover, the government has been emphasising on efficiency improvements within the power generation and distribution companies to reduce operational costs.

Additionally, there would be a push towards gradual adjustments of electricity tariffs to better reflect the actual cost of generation, the MoF official said, with a reference to the IMF's suggestion to this effect.

While the move towards reducing subsidies is seen by some economists as a positive step towards fiscal consolidation and promoting a more sustainable energy sector, concerns remain about its potential impact on consumers.

Any significant upward adjustment in electricity tariffs could put a strain on household budgets and potentially affect industrial competitiveness.

"The reduction in subsidies is a double-edged sword," said Dr Fahmida Khatun, a leading economist and Executive Director at the Centre for Policy Dialogue (CPD).

"While it's crucial for the long-term financial health, the government must carefully manage the transition to avoid sharp price hikes that could negatively impact the economy and the general public."

Stakeholders in the power sector, including generation companies, distribution entities, and consumer groups, will be closely watching the developments and their potential implications.

The government is expected to outline its strategy for mitigating any adverse impact of reduced subsidies, which could include targeted support for vulnerable populations and industries, as well as continued efforts to improve the efficiency and sustainability of the power sector, said an official at the Bangladesh Power Development Board (BPDB).

The focus will likely be on striking a balance between fiscal responsibilities and ensuring affordable and reliable access to electricity for all, he said.

However, government officials maintained that the subsidy is a necessary measure in the short- to medium-term to ensure energy security and support the nation's development goals.

They emphasize that alongside the subsidies, the government is also actively pursuing strategies to diversify the energy mix, enhance efficiency in power generation and transmission, and explore renewable energy sources to achieve greater energy independence and reduce the financial burden in the long run.

Further details regarding the specific mechanisms for subsidy reduction and potential tariff adjustments are expected to be revealed during the budget presentation and subsequent discussions, officials said.​
 

Members Online

Latest Posts

Latest Posts