Beyond a new terminal

Can Laldia make Bangladesh a mainline gateway?

1788305653722.webp

The project site of Laldia Container Terminal at Laldia, Patenga, in Chattogram Source: BSS Photo

When the foundation stone of the Laldia Container Terminal is laid on August 30, attention will understandably focus on the scale of the project: a $550 million foreign investment, a modern green terminal and a substantial addition to Chattogram Port's container-handling capacity. The government now expects construction to take about three years, with operations targeted for 2029. But Bangladesh should ask a bigger question. Can Laldia do more than handle additional containers? Can it begin changing Bangladesh from a predominantly feeder market into a mainline gateway?

That question matters because Bangladesh's maritime constraint has never been capacity alone. For decades, most long-haul containerised trade has depended on smaller feeder vessels connecting Chattogram with transshipment hubs such as Colombo and Singapore, from where cargo joins larger ships bound for Europe and North America. APM Terminals says Chattogram's present limitation of around 2,700 TEUs contributes to this dependence and that transshipment can add seven to 14 days to supply chains through additional handling and waiting.

LALDIA COULD ALTER THAT EQUATION: The terminal is being developed by APM Terminals, part of AP Moller-Maersk, under a public-private partnership with Chattogram Port Authority. Official project information puts the investment at about $550 million and planned annual capacity at more than 800,000 TEUs. More importantly, APM says the new facility could accommodate container ships of up to 6,000 TEUs-more than twice the size currently practical at Chattogram. The published design includes a 613-metre quay and 10.5-metre draught, alongside electrified and increasingly automated cargo-handling equipment.

WHY DOES 6,000 TEUS MATTER?: Not simply because a larger ship carries more boxes. Vessel size changes shipping economics. Larger ships can lower unit costs, improve equipment utilisation and give carriers greater flexibility in designing service rotations. But shipping lines do not deploy larger vessels because a country builds a bigger terminal. They deploy them when cargo volume, port productivity, schedule reliability and the economics of the entire service loop justify doing so.

This is where the discussion about Laldia should move beyond cranes, quay walls and storage yards.

APM Terminals itself has described the potential network effect. It argues that the ability to handle vessels of up to 6,000 TEUs could allow larger ships operating between Asia, Europe and North America to call at Chattogram and create possibilities for direct mainline connectivity. That should not be interpreted as an announcement that direct Europe or North America services have already been decided. Shipping networks are commercial decisions. But it means something important: the physical constraint that has helped keep Bangladesh predominantly within the feeder system could become substantially less restrictive.

CARGO CONCENTRATION THEN BECOMES CRUCIAL: Bangladesh already generates a large and relatively concentrated export base, led by ready-made garments. As exports grow and diversify into footwear, leather products, pharmaceuticals and other manufactured goods, the volume available to support larger vessels should also grow. The question is whether enough predictable cargo can be assembled week after week to support economically sustainable mainline calls.

EUROPE APPEARS THE MOST COMPELLING OPPORTUNITY: Instead of routing most European cargo through an intermediate Asian hub, a sufficiently productive Laldia could allow carriers to examine direct or substantially more direct service patterns between Chattogram and European gateways. A 6,000-TEU vessel does not need to operate as a simple Chattogram-Europe shuttle. Liner shipping is built around rotations. Bangladesh could form one node in a broader service linking Asian origins, Chattogram and European ports, with cargo carried on multiple legs of the same rotation.

This is why network economics matter more than looking at Bangladesh's export cargo in isolation.

APM Terminals and Maersk also bring an unusual dimension to the project. According to Bangladesh's PPP Authority, Maersk already handles almost 30 percent of containers moving into and out of Bangladesh. APM Terminals says it operates independently and serves shipping lines on non-discriminatory terms, as a successful terminal must attract multiple carriers. Nevertheless, being part of one of the world's largest integrated shipping and logistics groups gives APM deep knowledge of what global carriers require from a terminal: predictable berth windows, rapid vessel turnaround, equipment reliability, safety and dependable landside operations. If Laldia delivers those conditions, its influence could extend well beyond Maersk.

Other global carriers and alliances will make their own calculations. Once a port can accommodate larger vessels efficiently and sufficient cargo exists, competition itself can encourage new service configurations. That is how the significance of Laldia should ultimately be judged-not by whether one particular shipping line shifts its cargo there, but by whether the terminal makes Chattogram commercially more attractive across liner networks. The implications for Bangladesh's exporters could be considerable.

For garments, logistics time is increasingly part of competitiveness. A factory may manufacture efficiently, but those gains are partly lost when finished products spend additional days moving through an uncertain transshipment chain. APM specifically identifies improved schedule predictability and lower inventory costs among the potential network benefits of Laldia. For global fashion buyers managing short seasons, changing consumer demand and tightly controlled inventories, reliability can matter almost as much as freight rates.

That creates an important policy perspective. Bangladesh should not assess Laldia only through port dwell time. The more meaningful measure is factory-to-store time.

If a highly productive terminal, larger vessels and better network connectivity remove several days from the total supply chain, the economic benefit travels far beyond the port. Exporters gain reliability, buyers can carry less buffer inventory, manufacturers can respond faster to orders, and Bangladesh becomes a more attractive sourcing location.

North America represents a more ambitious second horizon. Regular direct connectivity to the US East or West Coast would require sufficient cargo, appropriate vessel deployment and a commercially viable wider rotation. It would be premature to predict such a service today. Yet once Chattogram can reliably handle vessels in the 6,000-TEU range, the idea moves from being constrained principally by port capability to being a question of network economics. APM itself includes North America when describing the mainline possibilities created by larger vessel access.

None of this, however, is guaranteed by the groundbreaking ceremony.

A world-class terminal cannot compensate indefinitely for weaknesses elsewhere in the logistics chain. A vessel that turns around rapidly at Laldia gains little if containers are delayed by customs procedures, fragmented information systems, congested roads or inefficient inland movements. Bangladesh therefore has three years before the planned opening to modernise the ecosystem surrounding the terminal.

Rail connectivity deserves particular attention. Bangladesh is simultaneously moving towards a wider network of rail-based inland container facilities, with Dhirasram intended to increase container movement by rail between the Dhaka industrial region and Chattogram and other locations also being considered for inland logistics development. Yet the experience of Patenga Container Terminal illustrates the limitation of developing a modern maritime terminal without direct rail connectivity: containers destined for the inland rail network cannot move seamlessly between ship and rail at the terminal itself. Laldia should not inherit the same structural constraint.

This is not an issue for APM Terminals alone to solve. It requires coordination between Chattogram Port Authority and the Ministry of Shipping on one side, and Bangladesh Railway and the Ministry of Railways on the other. Before Laldia becomes operational, the government should determine how the terminal will connect physically and operationally with the emerging rail-ICD network, including Dhirasram and future inland logistics nodes. If Laldia succeeds in attracting larger vessels and concentrating greater volumes of containers at each call, relying predominantly on trucks to evacuate that additional cargo would simply transfer congestion from the waterside to the landside. A mainline maritime gateway needs a mainline inland corridor behind it.

Customs processes must become genuinely digital rather than merely computerised. Port, Customs, shipping lines, freight forwarders, ICDs and other actors need interoperable data exchange. An effective Port Community System should reduce repeated data submission and physical intervention.

Laldia should likewise be understood alongside, rather than in competition with, Bangladesh's other maritime investments. Its location and 6,000-TEU capability can address an immediate need for a higher-performance container gateway at Chattogram. Matarbari, with its deeper-water potential, belongs to the country's longer-term maritime architecture. The strategic task is to connect these maritime gateways with railways, inland terminals and industrial centres as parts of one national multimodal logistics network.

There is also a reason to avoid excessive celebration before construction begins. Bangladesh has often equated infrastructure announcements with economic transformation. Laldia should face a tougher test. APM Terminals says its performance commitments cover vessel turnaround, container dwell time, equipment availability, environmental compliance and customer satisfaction. Those outcomes-not simply completion of civil works-should receive public attention once the terminal begins operating.

Ultimately, however, an even bigger performance indicator exists: connectivity.

Does Laldia attract larger vessels? Does it reduce dependence on transshipment for suitable trade lanes? Do regular mainline services emerge? Does factory-to-store time fall? And do international buyers begin to see Bangladesh as a more reliable sourcing origin because its maritime gateway has improved?

For decades, Bangladesh has competed internationally by learning to produce goods more efficiently. The next stage of competitiveness will depend increasingly on moving those goods more efficiently.

When the foundation stone is laid at Laldia on August 30, Bangladesh will formally begin building a new container terminal. Whether it is also beginning the journey from feeder market to mainline gateway will be decided not by the ceremony, nor by the number of cranes eventually standing on the quay, but by the shipping networks that follow.

Ahamedul Karim Chowdhury, maritime, logistics and supply chain policy analyst | Former Head of ICD Kamalapur & Pangaon ICT.​
 
I don't believe Bangladesh can become a mainline Gateway for container traffic.

Bangladesh is a large source for such container traffic at both Chittagong but storing and exchanging multiple berths and terminals for large volume regional container traffic is too much to handle a la Singapore or Colombo. Add to that how shallow Chittagong area draft is, which limits which mother vessel can dock, and you've got severe problems.

Matarbari may be a better deep draft option, however there is not enough jetty space there currently and expansion to reasonable scaling could take many years. Matarbari, Chittagong and Mongla will all three find it very challenging to deal with local export container traffic for the next decade, the way export is expanding at this time.
 
Last edited:

Cox's Bazar Airport almost ready to handle large aircraft


1790055738156.webp

Photo courtesy: Mamunur Rashid Kazi via Wikipedia

Development works on Cox's Bazar Airport are nearing completion, with the authorities expecting to inaugurate the upgraded airport in late October.

The Civil Aviation Authority of Bangladesh (CAAB) authorities have reported almost 99 per cent progress on the physical works of the airport's passenger terminal building while its runway expansion project also advanced 91.65 per cent as of August-end.

"If everything goes accordingly, the airport is expected to handle international flights and larger aircraft more efficiently by the end of next month (October)," said an official.

The international passenger terminal building, being developed at a cost of approximately Tk 3.62 billion, has already seen most of its major construction and installation works completed.

Facilities of the 17,956-square-metre terminal include an international departure lounge with a capacity of 450 passengers, boarding bridge, lifts, escalators, conveyor belts, check-in counters and immigration facilities, according to the CAAB.

The project also includes an arrival lounge, security and communication systems, internal roads, a pump house, deep tube-well, and other supporting infrastructure. Works on 35 VIP and 90 general car parking spaces were also under way.

The terminal project is scheduled for completion by December 2026, with cumulative physical and financial progress reaching 98.97 per cent and 93.78 per cent respectively.

Meanwhile, the runway expansion project is being implemented to make the airport suitable for wide-body aircraft operations. Under the project, the existing 9,000-foot runway has been extended to 10,700 feet by reclaiming 43 hectares of land from the sea, sources said.

The runway expansion has already achieved 91.65 per cent physical and 83.77 per cent financial progress, they mentioned.

Once completed, the extended runway is expected to facilitate safer take-off and landing of wide-body aircraft, including Boeing 777-300ER and Boeing 747-400 aircraft. It will also support increased international and domestic passenger and cargo operations.

A separate project is also under way to prepare the design and feasibility studies for transforming Cox's Bazar Airport into a full-fledged international airport and an aviation hub.

The proposed second-phase development envisages international-standard passenger terminal facilities, a control tower, administrative building, car parking, approach roads, STP, jetty, cargo complex, convention and business centre, general aviation facilities, aviation training centre, airport quarantine hospital, parallel taxiway, apron and refuelling system on 682 acres of coastal land.

The overall development is aimed at improving direct air connectivity between Cox's Bazar and Dhaka as well as other major domestic and international destinations, supporting the growth of tourism and increasing passenger and cargo movement through the airport.

At present, 28 to 30 domestic passenger aircrafts take off from or land at the Cox's Bazar airport daily.

Contacted, CAAB Member (Air Traffic Management) Air Commodore Noor-e-Alam said the facility will be fully ready to operate international flights.

"We have informed all the stakeholders and airlines about the Cox's," he mentioned.

Earlier in October last year, the airport's international status was annulled just 11 days after its official announcement, as there was insufficient airline interest in operating international flights and the facility lacked commercial viability at the time.​
 

Dhaka airportโ€™s 3rd terminal cost rises to Tk 222.13b


1790723300132.webp


The cost of the Hazrat Shahjalal International Airportโ€™s third terminal project has increased further, with Tk 6.67 billion required for 30 months of maintenance between January 2025 and June 2027, even though the terminal has yet to begin full-scale operation.

State Minister for Planning Zonayed Abdur Rahim Saki said the additional expenditure also includes costs for settling contractual disputes, completing outstanding works and installing facilities that were not included in the original project scope.

Briefing reporters after Tuesdayโ€™s ECNEC meeting, Saki said the government has set December 16 as the target for opening the third terminal, but some essential works will continue until June 2027.

The meeting approved an enhancement of Tk 8.47 billion; in total costs Tk 222.13 billion in the third price amendment, whereas it was Tk 213.65 billion in the second price amendment.

โ€œThe terminal will be inaugurated partially on December 16, but some works that are essential for operation will be completed by June 2027,โ€ Saki said.

Saki said the latest revision includes Tk 6.67 billion for 30 months of maintenance from January 2025 to June 2027 following the expiry of the defects notification period.

He said another Tk 2.94 billion has been added following recommendations of an amicable settlement committee to resolve disputes arising from variations in the construction contract.

The revised project also covers several outstanding components, including VIP and VVIP facilities, performance testing of the cargo handling system, the baggage handling system, water and sewage treatment plants, the explosive detection system (EDS) and UPS supply for EDS.

Additional expenditure has also been incurred for equipment maintenance and consultancy supervision, he said.

The state minister said 228 consultants, including 16 foreign and 212 local consultants, are involved in the relevant works, with the additional consultancy cost estimated at Tk 196.7 million.

The projectโ€™s tax component has meanwhile been reduced by Tk 1.34 billion, he said.

Saki said some facilities essential for operating a modern international airport were absent from the original project scope.

โ€œFor example, high-speed internet connectivity across the terminal area is essential. Immigration facilities also require equipment and systems, not simply personnel standing at counters,โ€ he said.

He said such omissions could occur even after feasibility studies, as the detailed design stage can reveal requirements that were not adequately reflected in the initial project documents.

The state minister said the government was therefore working to reform the feasibility study process so that project estimates and designs are more accurate from the beginning.

He said the government has already initiated steps to make agencies conducting feasibility studies more accountable and prevent feasibility studies from becoming a routine exercise carried out merely to fulfil procedural requirements.

Saki said proposals for these reforms had been prepared based on the experience of the Planning Ministry and line ministries and would be placed before the National Economic Council for approval.

He also said the government had issued clear instructions that project deadlines should not be extended without valid reasons.

โ€œWhenever a project is extended without a logical reason, those responsible will be brought under accountability,โ€ he said.

The Implementation Monitoring and Evaluation Division has already submitted investigation reports on eight projects, while reports on another three to four projects are expected shortly, he said.

The reports are being sent to the Prime Minister and concerned ministries for necessary action, he added.

Regarding major cost increases in other large projects, including MRT Line-1 and MRT Line-5 North, Saki said changes between preliminary feasibility studies and detailed designs can significantly affect project costs.

He cited underground construction as one factor behind the increased cost of metro rail projects, saying the geological characteristics of Dhaka have required some stations to be constructed at substantially greater depths than initially envisaged.

For the third terminal, however, he stressed that the latest increase had been broken down into specific components, including maintenance costs, additional facilities and settlement of contractual disputes.​
 

Govt seeks private investment to expand Pangaon terminal

Dwaipayan Barua

1790811830138.webp



Amid increasing container flow at the Pangaon Inland Container Terminal (PICT) in Dhaka, the Chittagong Port Authority (CPA) has taken the initiative to expand facilities at the terminal, which has failed to attract exporters and importers for years.

Average monthly container handling at the terminal, which stood at 242 twenty-foot equivalent units (TEUs) in 2024 and 366 TEUs in 2025, rose to around 900 TEUs in the seven months to August this year after the government handed over the terminal to a foreign operator, Switzerland-based logistics firm Medlog.

Against this backdrop, the CPA has invited private firms to develop and operate cargo and container handling facilities on 22 acres of land that remains vacant.

The port authority seeks private investment to manage, develop, supply, maintain and operate the facilities on the vacant land for 22 years, according to a tender published on September 22.

โ€œWe have taken the step for proper utilisation of the vacant land,โ€ said CPA Secretary Syed Refayet Hamim.

The Pangaon ICT was built on the bank of the Buriganga River in Keraniganj in 2013 jointly by the CPA and the Bangladesh Inland Water Transport Authority (BIWTA) at a cost of Tk 154 crore. It was intended to ease pressure on the Dhaka-Chattogram highway and railway corridors caused by cargo movement.

The CPA took a lease of 48.24 acres of land from the BIWTA to develop the terminal.

The current facility, under the management of Switzerland-based logistics firm Medlog SA, covers 26 acres. There are 22 acres of vacant land beyond the current facility, according to CPA Secretary Refayet.

The terminal had struggled to attract businesses transporting containerised cargo to and from Chattogram Port because of high inland water transport costs, lengthy customs clearance and other obstacles.

The situation has improved since Medlog Bangladesh Private Ltd, a concern of Medlog SA, started operating the terminal on January 17 this year.

As per the tender, interested firms, including their parent or holding companies, must have at least five years of experience in loading and discharging containers to or from vessels, according to the tender document.

They must also have experience in handling, storing and delivering containers and containerised cargo using their own equipment and manpower, with an annual handling capacity of at least 70,000 twenty-foot equivalent units (TEUs) at any inland river terminal or river port at home or abroad.

ATM Anisul Millat, managing director of Medlog Bangladesh, said container transport through the terminal had already exceeded the total annual throughput of 4,400 TEUs by June this year. He said his firm was interested in participating in the bidding to manage and develop the 22 acres of vacant land at the terminal.​
 

Govt approves 15-year deal to hand over Chattogram Portโ€™s NCT to foreign operator

Economic affairs committee's approval didn't disclose the name of the foreign operator

Star Business Report

1790897500620.webp

File Photo

The government on Thursday decided to hand over the New Mooring Container Terminal (NCT) of Chattogram Port to an international terminal operator as it approved the draft concession agreement for the operation and maintenance of the much-talked-about terminal.

The Cabinet Committee on Economic Affairs on Thursday gave approval to the draft concession agreement for 15 years, placed by the Shipping Ministry. The concession agreement will also include the Overflow Container Yard (OCY) of NCT.

The development comes amid protests by different sections, including the Chattogram Bandar Rokkha Songram Parishad, a pro-ruling party workers' platform, opposing the handover of the terminal to a foreign operator.

The economic affairs committee's approval did not mention the name of any foreign operator, and neither Chattogram Port Authority nor Invest Bangladesh Authority commented on when the agreement is expected to be signed.

However, in a statement signed by Mohammad Humayun Kabir and Mohammad Ibrahim Khokon, joint coordinators of the platform, they mentioned the name of the multinational operator DP World and alleged that claims about NCT's equipment being obsolete and equipment availability falling below international standards were misleading and aimed at facilitating the handover.

It said giving DP World operational control could create long-term economic and security risks, including the outflow of revenue and foreign currency and possible job losses for port workers.

The Bandar Rokkha Songram Parishad said NCT generated around Tk 4,500 crore in revenue and Tk 2,500 crore in net income in fiscal 2025-26, and warned that a concession could reduce the governmentโ€™s earnings and affect jobs at the port.

The platform urged the government to reconsider the draft agreement, which it said had recently been approved by the Cabinet Committee on Economic Affairs.

The Daily Star tried to reach Shipping Secretary Zakaria by phone but could not reach him.

The proposal to hire a foreign operator for the NCT, the largest container-handling facility at the countryโ€™s main seaport, Chattogram Port, has been under consideration for several years. The process began in 2019, while the Cabinet Committee on Economic Affairs gave in-principle approval to appoint an international private operator under the PPP model in March 2023.

The interim government was close to finalising a deal with DP World to operate NCT. But in the wake of a wildcat strike enforced by port employees and workers, it suspended the move just before the parliamentary election held in February this year. The new government has continued the talks, according to the fourth joint public-private partnership platform meeting of Bangladesh and Dubai held in Dubai in April this year.

In June, Chattogram Port Authority formed a 12-member support team to assist the negotiation committee on the NCT.

The terminal, currently operated by Chittagong Dry Dock Ltd, a Bangladesh Navy-controlled company, handles over 40 percent of the port's total container throughput, recorded at 3.5 million TEUs in fiscal year 2025-26.

The NCT, built at a cost of about Tk 2,000 crore in 2007, contains five jetties and 14 of Chattogram Port's 18 quayside gantry cranes.

The NCT will get the fourth foreign operator at Chattogram Port after the appointment of three other foreign firms. In June 2024, operator RSGT International (RSGTI) started handling the Red-Sea Gateway Terminal (RSGT), formerly known as Patenga Container Terminal. By the end of August this year, APM Terminals, a subsidiary of Danish shipping group AP Mรธller-Maersk, began construction of Laldia Container Terminal in Chattogram. At the beginning of this year, Switzerland-based logistics giant Medlog started handling Pangaon Inland Container Terminal (PICT) in Dhakaโ€™s Keraniganj.​