Beyond locomotive crisis
The untapped promise of Dhaka-Mongla rail corridor


1792626495371.webp



Bangladesh's rail-based container logistics is facing an uncomfortable contradiction. On the eastern network, a shortage of serviceable metre-gauge locomotives is disrupting the established Chattogram-Dhaka container service. Meanwhile, substantial investment in broad-gauge rail connectivity across the Padma Bridge and towards Mongla Port has yet to produce a regular container freight service. This is more than a railway operating problem. It raises a national logistics question: can Bangladesh use infrastructure already built to create a second reliable rail-linked maritime gateway for Dhaka and surrounding industries?

The urgency is difficult to ignore. An investigation published by a local daily on October 15 reported that 18 of 30 relatively new Hyundai Rotem locomotives had become inoperative within four years of entering service, partly because of unavailable spares and technical support. According to the same account, only two of eight container trains were operating regularly. Eastern Zone container-train trips fell from 2,878 in FY2022-23 to 1,467 in FY2025-26. This undermines the reliability traders require.

The government has responded. On October 7, ECNEC approved a Tk 2,769.86-crore project to acquire 30 additional metre-gauge locomotives, with implementation scheduled through December 2029. Procuring these engines is necessary: the eastern network still depends on metre gauge. But new purchases cannot repair existing engines or guarantee early delivery. The long procurement horizon creates a compelling case for a parallel operational strategy.

AN INVESTMENT AWAITING A SERVICE: That strategy should begin with the Dhaka-Mongla broad-gauge corridor. The Padma Bridge Rail Link was expressly designed to connect Dhaka and Jashore through a new broad-gauge alignment; its official objectives include national and international freight and broad-gauge container trains. The Khulna-Mongla railway connects the port with the wider western network. Together, these investments create a possible rail route between Dhaka, Jashore and Mongla, subject to operational verification.

Yet the final step-from railway alignment to commercial freight operation-remains largely missing. Reports in September 2026 still described the Khulna-Mongla line as operating without regular freight trains. In effect, one part of the railway system is losing container services because of locomotive constraints, while another possesses substantial new infrastructure without sustained freight traffic. It warrants a corridor-readiness assessment, not assumptions about immediate cargo diversion.

The distinction matters. A through container train requires more than compatible rails. Bangladesh Railway must confirm available broad-gauge locomotives and suitable flat wagons, axle loads, signaling, train paths and locomotive rotation. At Mongla, containers need efficient transfer between ships, customs-controlled yards and rail wagons. At Dhaka, an inland terminal needs track access, handling equipment, storage, roads, security and customs arrangements. Every extra lift or unnecessary road transfer may destroy the supposed advantage of rail.

KAMALAPUR MUST NOT BECOME A CASUALTY: This question is particularly consequential for ICD Kamalapur, historically the centre of Dhaka's rail-linked container movement. Its present difficulties cannot be resolved simply by announcing that broad-gauge trains will arrive from Mongla. Its sidings and loading arrangements need to be checked for broad-gauge operations. Until that is demonstrated, the proposed corridor must not be represented as an immediate replacement for the Chattogram-Kamalapur metre-gauge service.

There is also a longer-term terminal-location issue. Kamalapur faces land and urban-access constraints. Dhirasram has been advanced as a future ICD, with a planned dual-gauge rail link from Pubail, but its cost, timing and access deserve scrutiny. Pubail itself also merits objective comparison as an alternative or complementary terminal site because of its location on the existing corridor. The national priority should be a functional, commercially accessible Dhaka inland-container network, not unconditional commitment to one location. In the transition, Kamalapur's operating capability must be maintained while options for a broad-gauge interface are assessed.

MONGLA'S MARKET MUST BE EARNED: There are promising signs at Mongla. The port handled 29,714 TEUs in FY2025-26, up 38.49 per cent year on year, alongside rising cargo and vessel activity. Nevertheless, this volume remains modest relative to the main container gateway at Chattogram. The opportunity is therefore to cultivate a viable additional traffic stream, rather than assume an automatic diversion of established shipping services.

In September, the Bangladesh Knitwear Manufacturers and Exporters Association and Mongla Port Authority discussed wider use of Mongla for garment exports. BKMEA's insistence on reliable schedules and competitive charges should be taken seriously. Shipping lines decide port calls according to cargo volumes, vessel economics and network connections; exporters choose routings according to confirmed sailing dates and buyers' deadlines. The navigability of the Pashur channel, maintenance dredging, vessel limitations, shipping frequency and empty-container repositioning are equally material. Rail will become attractive only if the entire chain from factory to vessel-and from vessel to consignee-performs predictably.

There is consequently a strong case for rail-linked container-handling and off-dock or container freight station capacity in the Mongla area, subject to customs licensing, port planning and commercial feasibility. Such facilities could consolidate garment exports, handle eligible import cargo, support container stuffing and de-stuffing, and reduce avoidable port-area delays. Licensing and investment must reflect actual terminal functions. The 2026 customs rules for private ICDs and CFSs make such regulatory diligence especially important.

Over time, a functioning Mongla rail interface could also serve suitable cargo from Jashore-Benapole, Ishwardi and northwestern industrial centres through the wider broad-gauge network. Such extensions should follow verified origins, destinations and train paths, rather than optimistic lines on a map. The longer-term opportunity is a multi-gateway inland-depot network, not merely a Dhaka-Mongla shuttle.

WHAT NEIGHBOURS AND GLOBAL PORTS HAVE LEARNED: India offers a relevant operational lesson. Its Dedicated Freight Corridors separate substantial volumes of freight from passenger-dominated routes, but their benefits also depend on terminals, wagons and customer-facing services. An August 2026 Indian government statement reported an average of approximately 443 trains a day on the two corridors. Under the Gati Shakti Cargo Terminal programme, 142 terminals had been commissioned, with private investment supporting rail-connected cargo facilities. Bangladesh need not copy India's scale, but must match infrastructure to paying demand.

A second lesson comes from neighbouring Nepal. In July 2026, a direct container freight train travelled from Kolkata Port to Biratnagar Customs Yard under a revised India-Nepal transit arrangement. Its significance lies in linking railway movement with the necessary customs and operational permissions, avoiding an unnecessary handling break. The message for Bangladesh is that agreements between railway, port and customs authorities are essential components of infrastructure utilisation.

China provides a further illustration: Ningbo-Zhoushan port moved more than two million TEUs by sea-rail intermodal transport in 2025, supported by scheduled services and inland dry ports. Its scale is not comparable with Mongla's, but the principle is universal. Customers purchase integrated services, not isolated railway journeys. A port-to-ICD corridor succeeds when cargo can be booked, monitored, cleared and delivered with confidence.

A PRACTICAL TEST OF LOGISTICS POLICY 2025: The National Logistics Policy 2025 already provides the institutional basis for this approach. Section 3.2 calls for rail links to ports, industrial areas and ICDs; phased metre-gauge conversion; scheduled freight trains; private participation; and optimum utilisation of existing infrastructure. Its seaport provisions encourage integrated connections and off-dock and inland-depot facilities. Most importantly, the policy requires time-bound implementation, not simply another inventory of proposed projects.

The government's five implementation working groups-covering multimodal infrastructure, investment, trade facilitation, digitalisation and skills development-could make the Dhaka-Mongla corridor a practical joint work programme. The infrastructure group should lead an operational audit; the investment group should test a terminal and train-service business model; the trade facilitation group should address bonded movement and inland customs clearance; the digitalisation group should organise container visibility across railway, port and customs systems; and the skills group should address terminal operations and equipment maintenance. Bangladesh Railway, Mongla Port Authority, customs, terminal operators, shipping lines and cargo owners must participate from the outset.

Private participation should be commercially explicit. Bangladesh Railway could provide network access and traction under an agreed haulage framework, while an appropriately selected operator invests in wagons, terminals or logistics services where viable and legally permissible. Transparent access charges, service standards, liability rules and long-term arrangements would be needed. India's experience with private container-train participation shows that state ownership of track need not exclude competitive investment in the freight business. Commercial viability must decide the structure.

FROM FEASIBILITY TO A WORKING TRAIN: A focused, 90-day joint assessment should be the starting point. It should map a physically operable route, check rolling stock and terminal capacity, verify a suitable Dhaka railhead, estimate the investment needed at Mongla and identify customs procedures. The same exercise should compare the full logistics cost of Mongla with Chattogram, including ocean freight, sailing frequency, rail haulage, handling, empty containers, road delivery and the financial consequences of delays. Any claimed savings or emissions benefits should emerge from this comparison, not from assumptions about railway transport being universally cheaper.

Within the following six months, the authorities should seek genuine volume commitments from exporters, importers, shipping agents and freight forwarders. If the operational and commercial tests are passed, one or two scheduled container train pairs each week could be trialed, initially using existing suitable facilities rather than waiting for an elaborate new depot. The pilot should be judged by train punctuality, end-to-end transit time, wagon turnaround, container dwell, delivered cost, safety and repeat customer demand. If tests fail, the design must change before further investment.

The Dhaka-Mongla proposition should therefore complement, not compete with, efforts to restore Chattogram-Kamalapur services and strengthen the country's primary port corridor. It would diversify maritime access, provide another choice to suitable cargo owners and use the broad-gauge network more productively. It would not remove the need for metre-gauge locomotive maintenance, nor guarantee that shipping lines will relocate services.

Bangladesh has spent heavily to connect its regions by rail. The next measure of success should not be kilometres of track inaugurated but containers moved reliably at a competitive cost. The locomotive crisis offers a reason to act urgently; the Dhaka-Mongla corridor offers a credible opportunity to test whether the National Logistics Policy can turn existing assets into an integrated freight service. The task now is to prove that proposition with a working train, a functioning terminal and customers who return.

Ahamedul Karim Chowdhury is maritime, logistics and supply chain policy analyst. Adjunct Faculty, Bangladesh Maritime University.​
 

Capacity building of BR workshops


1793060356518.webp



Indifference to development of the Bangladesh Railway (BR) could not be more glaring if the capacities of its three workshops at Saidpur, Pahartali and Parbatipur are taken into account. In a small country with an oversize population, the misplaced priority for development of road communication based on long-route and imported luxurious buses is the result of a wrong policy pursued by successive governments. Cheaper, safer, faster and relatively more comfortable, railway is a mass transportation service. This is exactly why railway networks have been expanded alongside radical improvement of services all across the world. But in Bangladesh, it has followed a retrogressive course over the past decades. Only recently did the BR receive some renewed attention. When there was a need for expanding the railway network, its services on several routes were either curtailed or abandoned. Several rail stations on the existing routes too fell into disuse.

Against this dismal picture of the BR, the initiative taken to bolster the capacity of the Saidpur railway workshop in Nilphamari district is highly laudable. The authorities have at last recognised that dependence on imported passenger coaches makes no sense particularly when the government plans to expand and modernise railway service. Under a foreign-aided project to be funded by the Jeddah-based Islamic Development Bank (IsDB), the workshop will be upgraded for assembling and manufacture of passenger coaches. Insiders are optimistic that addition of advanced machinery will not only manufacture enough passenger carriages and freight wagons to meet the domestic need but also be able to export coaches. This sounds far too ambitious at this moment. Before giving a thought to exporting coaches, proper use of the proposed fund amounting to US$60 million for upgrading the workshop has to be ensured.

Capacity building is more than just procurement of machines and equipment. During an earlier initiative for modernisation of the workshop, machinery worth about Tk1.53 billion was installed only to be underused. Responsible for this was the lack of technical and skilled hands. The workshop recruited only 716 staff members against 2,859 vacant posts. Details of the recruited staff are not known but, as reported, none among them are skilled enough to operate many of those installed machines. There is no guarantee that this will not happen again. Without readying skilled operators, procurement of sophisticated machines is a futile exercise. Staff members should be trained abroad to make sure they can efficiently handle the advanced machines and equipment. Alternatively, such operators can be hired from abroad for a certain period during which local technicians can receive on-job training.

Again, assembling is one thing and manufacture of whole new coaches is an altogether different proposition. Those who have initiated the move must be clear about the agenda. To assemble imported parts, there is no need for the deeper knowledge and special skills required for producing passenger carriages or freight wagons. Moreover, the workshop yard has to be expanded in case of manufacture of such coaches and wagons. Similar programmes should be taken for capacity building of the two other workshops. Apart from massive investment, the need for iron billet and other materials will prove critical. In fact, development of allied industries is likely to happen in order to maintain steady supply of the various fitting materials and gadgets needed to furnish passenger coaches. If the project is undertaken seriously, it will spur economic activities and create job opportunities for a large number of people.​
 

Govt eyes electric train services on Dhaka-Chittagong route

A Tk3,500 crore pilot project on the Narayanganj-Dhaka-Joydebpur corridor will pave the way for expansion, with trains designed to run at up to 140kph

1794619636703.webp

Representational Photo: Collected

The government plans to extend electric train services to Chittagong after launching a pilot project on the Narayanganj-Dhaka-Joydebpur corridor as part of efforts to modernise the country's railway network.

The expansion would bring electric trains to the busy Dhaka-Chittagong route, improving passenger services, speeding up freight transportation and reducing dependence on fossil fuels.

Bangladesh Railway Chief Planning Officer Engineer Md Rafiqul Islam said the government plans to introduce electric multiple-unit (EMU) trains capable of running at speeds of up to 140kph.

The pilot project has received approval from the Executive Committee of the National Economic Council (ECNEC), with an estimated cost of Tk3,500 crore. The Asian Development Bank (ADB) is expected to provide most of the financing, while the government will cover domestic costs, including duties and VAT.

The tendering process is expected to be completed by 2027, with major construction work scheduled to progress from mid-2028.

A total of 16 EMU train sets will be imported for the pilot corridor. The trains will have driving facilities at both ends, allowing them to operate without being turned around.

Rafiqul Islam said the Dhaka-Chittagong corridor was a priority because of its importance for passenger and freight movement, connecting the capital with the country's main seaport and commercial centres.

Currently, only 60,000-70,000 twenty-foot equivalent units (TEUs) of containers are transported annually by rail from Chittagong to Dhaka, accounting for around 3% of total container traffic.

The Dhirashram Inland Container Depot project aims to increase annual rail container transportation to 450,000 TEUs, creating scope for greater freight movement by rail.

To support railway electrification, Bangladesh Railway is also developing infrastructure along key routes. Construction of the third and fourth railway lines between Dhaka and Tongi is progressing, while double-line construction on the Tongi-Joydebpur section has been completed.

Additional land is being acquired at Joydebpur for an EMU depot and workshop. Meanwhile, metre-gauge lines on the Tongi-Akhaura and Laksam-Chittagong routes are being converted into dual-gauge double lines.

Rafiqul Islam said Bangladesh Railway was prioritising electric trains capable of running at 140kph rather than bullet trains, which can reach speeds of around 350kph.

Introducing bullet trains would require an estimated Tk150,000-250,000 crore, alongside major land acquisition and other challenges in the country's densely populated landscape, he said.

Electric trains are also expected to reduce carbon emissions, air pollution and fuel consumption. Bangladesh Railway is assessing the potential environmental benefits and opportunities to earn carbon credits through internationally recognised mechanisms.

The pilot corridor is expected to lay the groundwork for a wider electric railway network, with Chattogram identified as the next major expansion destination.​
 

Dangerous development on the railway front


1794783258984.webp



Bangladesh's obsolete railway infrastructure itself is a cause for concern. Responsible for this is the decades of indifference of governments to this mass and globally popular transportation system. Over the past few years, however, the railway has received some attention but it is not enough because the massive investment it needs is simply missing. Now three coordinated internal and restricted reports prepared by four departments of the eastern zone of the Bangladesh Railway (BR) expose the danger facing it. Treated it as a lead story in its Sunday issue, a Bangla contemporary has pointed to the risks running by the railway, particularly on the Dhaka-Chattogram rail route.

In the past three months, as many as 76 unwanted incidents have been reported. Of them, 51 account for technical faults and negligence of staff members of the BR. But the rest 25 are deliberate acts of sabotage or theft. In such incidents, the devices at turnover points were missing, at other points, the signalling systems with the transformers were taken away. These are in addition to the earlier reported incidents of dismantling of nuts and bolts, fish plates and clips. Signalling system, motor and wires or cables installed at track points, clips and nuts and bolts are very costly with high demands. Theft of such implements cannot be ruled out.

However, when wires and cables of the sensitive signalling system are just left snapped and nuts and bolts unscrewed before leaving those on trackside, the efforts behind are surely suspect. Also driving and detection rods used for safely change tracks near Vatiary Station were broken on July 13 last. No matter if these are acts of theft or sabotage, serious accidents may occur unless identified immediately. Because of theft of wires or cables, the signalling system malfunctions and if devices at the turnover points are broken or stolen, trains cannot change tracks. Trains on the same track from opposite directions can collide head-on or run the risk of collision from behind.

Fortunately, a number of such incidents were detected before the worst could happen. In some cases, railway services were disrupted on account of such incidents. On October 23, a freight train got a wrong signal before entering the Bhairab Railway Junction and ramming into Egarsindur Express. That accident left 22 people dead more than 100 others injured. Similarly, in March this year seven coaches of another express train were derailed near Hasanpur station in Nangolkot of Cumilla.

Train journeys were supposed to be more comfortable and safer compared to other modes of transportation. But the service has been rendered hazardous by some notorious elements' rapacious acts. They either steal or just snap or dismantle sensitive railway implements and devices knowing full well what tragic consequences their acts can lead to. Accidents involving mass transports leave a large number of passengers dead and injured. Those who throw stones at running trains are mostly teenagers and they seem to have learnt from their elders engaged in acts of theft of railway property and sabotage.

It is challenging to bring the entire length of railway tracks under watch but unless effective vigilance is arranged for the areas known for theft and sabotage, rail journey cannot be safe and free of mental stress. The railway authorities should moreover install close-circuit-TV cameras in the railway track segments that are suspect. Vigilance teams should also be deployed there in order to bring an end to theft and sabotage.

Such acts fuel social instability. The rise of wicked elements over the past couple of years corroborates this fact. People do not feel safe anywhere in this country. The rising trend of mob violence changed its gear during the interim government of Muhammad Yunus because of the administration's inaction. There is no sign that the incumbent government is serious about taking the bull by the horns. But it should have in order to contain the law and order situation. If social anarchy is not dealt with an iron hand, not only does it consign society into turmoil but also harm the country's economy beyond repair.​
 

Railway plans to introduce electric trains
Tk 46.27cr sought for feasibility study, designs

Jahidul Islam . Dhaka

1795738796663.webp


Bangladesh Railway plans to introduce electric trains on 1,638 kilometres of railway across 12 groups of routes and branch lines, following approval of the Narayanganjโ€“Dhakaโ€“Joydebpur electrification project in August.

The railway ministry has sent a Tk 46.27 crore project proposal to the Planning Commission to assess the feasibility of electrification and prepare detailed designs for routes covering 263 stations.

The proposal says electrification could improve Bangladesh Railwayโ€™s finances by cutting energy and maintenance costs and raising revenue from passenger and freight services.

Using Indian Railwaysโ€™ energy consumption data and Bangladeshi diesel and electricity prices, the proposal estimates that electric trains would have 51.52 per cent lower energy costs for passenger services and 62.01 per cent lower costs for freight than diesel-electric trains.

Experts said that achieving the projected savings would require a reliable power supply, trained staff and regular maintenance of trains and overhead power lines. They also recommended developing domestic capacity to supply coaches.

Planning Commission officials said that the Executive Committee of the National Economic Council approved the Tk 3,822.51-crore project to introduce electric commuter trains on the 52.32-kilometre Narayanganjโ€“Dhakaโ€“Joydebpur route.

The project allocates Tk 1,680.19 crore to buy electric train sets and Tk 656.85 crore to build a maintenance workshop, with the two components accounting for 61.14 per cent of the total cost.

An earlier appraisal projected that the commuter service in 52.32-kilometre track would ensure an operating surplus of Tk 770.38 crore before capital costs and debt repayments.

The proposed study covers broad-gauge routes in the western zone and the Gendariaโ€“Bhanga and Chattogramโ€“Coxโ€™s Bazar sections in the eastern zone.

Consultancy services account for Tk 43.90 crore, or nearly 95 per cent of the proposed study cost, while Tk 1.62 crore is earmarked for vehicle hire.

The railway sees scope to expand commuter services around major cities and carry more agricultural and mineral products in the western zone, including freight through Mongla port and border points such as Benapole, Darshana and Rohanpur.

The proposal identifies tourism as a source of passenger demand on the Chattogramโ€“Coxโ€™s Bazar route.

Chilahatiโ€“Darshana is the longest section listed, at 319.24 kilometres with 65 stations, followed by Gendariaโ€“Bhangaโ€“Jashoreโ€“Benapole at 202.11 kilometres and Joydebpurโ€“Ishwardi at 169.62 kilometres.

The other routes include Parbatipurโ€“Panchagarh and Kanchanโ€“Birol, Abdulpurโ€“Rohanpur and Amnuraโ€“Chapainawabganj, Rupdiaโ€“Khulna, Padmabilaโ€“Singia and Phultalaโ€“Mongla, and Kashianiโ€“Gobra and Kashianiโ€“Bhatiapara.

Kashianiโ€“Poradaha, Majhgramโ€“Dhalarchar, Kalukhaliโ€“Bhanga and Pachuriaโ€“Goalando Ghat, and under construction Boguraโ€“Sirajganj are also on the list.

The study would assess the technical, financial, economic, social and environmental viability of electrifying each section and prepare land acquisition and resettlement plans where needed.

The railway would use the findings and engineering designs for grid connections, traction substations, overhead lines, control centres, depots and workshops to prepare section-wise investment proposals, cost estimates and tender documents.

Proper implementation of railway electrification could help reduce operating costs, said Bangladesh University of Engineering and Technology civil engineering professor Shamsul Hoque.

He said that the feasibility study should determine how many passenger and freight trains each route could support and whether the energy savings would justify the cost of buying trains, supplying power and maintaining the system.

A reliable power supply, trained staff, local servicing capacity and access to spare parts would be essential to keeping costs down, he added.​