[🇧🇩] Civilian/Military Nuclear Program in Bangladesh

[🇧🇩] Civilian/Military Nuclear Program in Bangladesh
105
5K
More threads by Saif

G Bangladesh Defense

BPDB still clueless about Rooppur N power plant tariff as test run begins

M Azizur Rahman

Published :
Jun 17, 2026 09:53
Updated :
Jun 17, 2026 09:53

1781669855134.webp


The lone buyer of electricity from the Rooppur Nuclear Power Plant (RNPP) is still unaware of the tariff it will have to pay for purchasing power from the country's first nuclear power facility.

"I don't have any information about how much the tariff of the RNPP will be," Chairman of the state-run Bangladesh Power Development Board (BPDB), Md Rezaul Karim, told The Financial Express (FE) on Tuesday.

The BPDB will be the sole purchaser of electricity generated by the Rooppur plant and will subsequently sell the power to different state-owned distribution companies.

Although the RNPP tariff has yet to be fixed and the overall costs remain undisclosed, authorities have started test operations of the plant after completing fuel loading on May 13.

The authorities aim to generate around 300 MW of electricity from Unit-1 of the RNPP by August.

"Despite repeated letters and queries to the Rooppur power plant authorities, we are yet to receive any information regarding the total project cost, operation and maintenance (O&M) expenses and other related costs, if any," the BPDB chairman alleged.

According to him, the BPDB has been trying for the past one and a half years to obtain information on the RNPP's costs to assess the tariff and determine whether the government will need to provide subsidies, as it does for many other power plants.

The RNPP tariff will be fixed as a bulk tariff, as the BPDB will purchase electricity directly from the plant authorities, he said.

"We also have not heard anything about the tariff of the RNPP," Chairman of the Bangladesh Energy Regulatory Commission (BERC) Jalal Ahmed told the FE on Tuesday.

He said the RNPP authorities have not yet submitted any proposal for fixing the nuclear power tariff. A public hearing may not be required to determine the tariff rate, according to the BERC chairman.

The BPDB chairman echoed the same view, saying that a public hearing may not be necessary because the RNPP is a cost-based project.

The tariff should be determined considering the plant's lifespan of around 60 years, he said.

Calculating the tariff based on a shorter lifespan could increase the tariff rate and place an additional subsidy burden on the government, he warned. The project director of the RNPP could not be reached for comment despite repeated attempts over the telephone.

When contacted, Consumers Association of Bangladesh (CAB) Energy Adviser Prof M Shamsul Alam called for forensic, technical and energy audits of the RNPP to uncover any irregularities and determine the project's actual cost before fixing the tariff. He also demanded that a detailed cost analysis of the RNPP be made public.

Alleging large-scale corruption in the project, he called for a proper investigation to identify and punish those responsible.

Only standard costs comparable to those of other nuclear power plants around the world should be considered when determining the tariff, he added.

Officials said Russia will supply fuel for the first three years under the existing contract. Thereafter, Bangladesh will have to import uranium to operate the Rooppur plant.

The RNPP has a design lifespan of 60 years, which can be extended by another 30 years through proper maintenance.

Financially, Rooppur is Bangladesh's largest single infrastructure project.

The plant's first unit is expected to enter commercial operation in January 2027, while full generation capacity of 2,400 MW from both units will be achieved after the second unit becomes operational.

The construction cost of the Rooppur project stands at US$12.65 billion, with Russia providing 90 per cent of the funding through a loan.

Construction of Unit-1 began on November 30, 2017, while work on Unit-2 started on July 14, 2018. Unit-1 was originally scheduled to begin operations in December 2022 and Unit-2 in October 2023.

However, the Covid-19 pandemic and payment-related complications arising from the Russia-Ukraine war delayed the commissioning of the project.​
 

IMED flags readiness gaps at RNPP
Faster coordination urged

JAHIDUL ISLAM

Published :
Jun 24, 2026 08:46
Updated :
Jun 24, 2026 08:46

1782276259164.webp


The Implementation Monitoring and Evaluation Division (IMED) has called for urgent coordination between the main Rooppur Nuclear Power Plant (RNPP) project and its four supporting projects, alongside faster procurement planning and the settlement of long-pending audit objections.

The planning ministry's monitoring agency has also recommended strengthening manpower deployment planning to ensure the timely commissioning and safe operation of the country's first nuclear power plant.

The recommendations were made in an IMED report following an inspection of the mega project.

Copies of the report were sent to the Ministry of Science and Technology, the Bangladesh Atomic Energy Commission (BAEC) and other relevant authorities, along with a set of observations and recommendations.

The inspection found that although the project had achieved 78.80 per cent physical progress and 74.29 per cent financial progress as of March 2026, several critical readiness gaps remain.

According to the Preliminary Safety Analysis Report (PSAR), the RNPP requires 2,090 personnel for the operation, maintenance and management of its two units.

However, the current staffing framework does not include personnel for the on-site fire station, security and physical protection division, and several service departments.

So far, 1,734 personnel have been recruited, including 1,636 technical staff. Of them, 1,290 have received training under the Russian general contractor framework, while 1,155 have been assigned to designated positions.

The report noted that the Russian contractor, Atomstroyexport, has not consistently provided the mandatory Level-2 annual work schedule since 2012, despite contractual obligations.

IMED observed that the absence of a detailed, time-bound work plan has hampered the monitoring of critical activities, procurement coordination and overall readiness planning for both units.

It recommended that the project office and the Ministry of Science and Technology take urgent steps to obtain a comprehensive manpower deployment plan, procurement schedule and materials supply plan from the contractor.

The inspection noted that Unit-1 has entered the advanced commissioning stage following fuel loading and is now progressing through phased start-up activities.

However, delays in earlier milestones have already pushed back the original commissioning target of December 2025.

The IMED review also assessed four supporting infrastructure projects linked to the RNPP, including off-site water supply, nuclear regulatory infrastructure, physical protection systems and external telecommunications networks.

Progress in these projects ranges from 40 per cent to 82 per cent, the report said, warning that uneven implementation of the support projects could affect operational readiness once the plant becomes fully operational.

The report also flagged 230 unresolved audit objections involving financial claims worth about Tk 295.6 billion, identified between 2017 and 2025. None of the objections has been fully resolved.

IMED urged the authorities to expedite the settlement process to ensure financial discipline and accountability in the project.

The monitoring agency further directed the project director to prepare a time-bound manpower deployment and procurement plan in coordination with Atomstroyexport, while ensuring stronger coordination between the main plant and its supporting projects.

The Ministry of Science and Technology has been asked to inform IMED within one month about the actions taken to implement the recommendations.​
 

Latest Posts

Back