- Copy to clipboard
- Thread starter
- #271
Payra power plant halts production for tests of new facility
Production cost at new facility to be lower than that of Adani, other plants
www.thedailystar.net
Payra power plant halts production for tests of new facility
Production cost at new facility to be lower than that of Adani, other plants
The Payra thermal power plant in Kalapara upazila of Patuakhali has halted production to conduct maintenance and facilitate the test commissioning of a neighbouring facility, according to officials of the 1,320-megawatt (MW) coal-fired power station.
They informed that the plant's first 660 MW unit was shut down for seven days from December 16 for the test commissioning of the nearby power plant run by RPCL- NORINCO International Power Limited (RNPL).
Meanwhile, the second unit was shuttered earlier on November 9 for three months for conducting major maintenance works, said Shah Abdul Mawla, project officer of the Payra power plant.
He said the newly-built RNPL power plant will begin production on a trial basis in January.
As such, power generation at the Payra power plant was halted to allow testing of the transmission lines of the new facility in Amtoli upazila of Barguna, he said.
The new plant is located on the banks of the Ramnabad river, just two kilometres north of the Payra power plant. Costing about $2.5 billion, its construction began in 2019 on some 950 acres of land.
The RNPL is a joint venture of Bangladesh's state-owned Rural Power Company Limited and China's state-owned Norinco International Cooperation Limited, with each having an equal stake.
To enable the test for commissioning the RNPL-run plant, the authorities of the Payra power plant allowed for their thermal power transmission lines to be kept shut, he added.
Selim Bhuiyan, managing director of the RNPL, said each unit of the two units of the new power station can produce up to 660 MW of electricity.
"But to begin operations, it is now necessary to conduct the test. For this, the Payra-Gopalganj 400 kV power transmission line will have to be shut down. Then, it will take up to 75 days for the commissioning," he added.
Bhuiyan also said they expect the new plant to begin contributing to the national grid on the first week of March and production at its second unit of equal capacity was expected to begin by the end of May.
Sources close to the project said the total installed capacity of the grid-based power plants in the country is about 27,740 MW.
Of this, the capacity of coal-based power plants is 5,683 MW. If the capacity of the RNPL-run plant is added, the total capacity of coal-based power plants would stand at 7,000 MW, they said.
Regarding coal stocks for the new power plant, Bhuiyan said when the plant starts generating electricity, 12,000 tonnes of coal would be required on an average per day for the two units.
An agreement has already been reached with Singaporean company Yantai to supply 1 million tonnes of coal.
Under that agreement, 1.28 lakh tonnes of coal have reached the new power plant. More coal will arrive in January. In this way, coal will be imported in phases according to demand.
He said in an attempt to minimise environmental damage, high-quality coal from Indonesia would be used in this new plant. It is a state-of-the-art power plant, where more electricity will be generated by burning less coal compared to conventional power plants.
Regarding the price of electricity, he said the production cost of this new plant will be lower than that of Adani, Rampal, Banshkhali and other thermal power plants.
Considering the current price of coal ($77), the price of electricity per unit can be around Tk 9.85 on an average.
Md Toufiq Islam, project director and chief engineer of the RNCL-run plant, said if everything goes well, the first unit would be fully operational by early March and the second unit by June.
Production cost at new facility to be lower than that of Adani, other plants
The Payra thermal power plant in Kalapara upazila of Patuakhali has halted production to conduct maintenance and facilitate the test commissioning of a neighbouring facility, according to officials of the 1,320-megawatt (MW) coal-fired power station.
They informed that the plant's first 660 MW unit was shut down for seven days from December 16 for the test commissioning of the nearby power plant run by RPCL- NORINCO International Power Limited (RNPL).
Meanwhile, the second unit was shuttered earlier on November 9 for three months for conducting major maintenance works, said Shah Abdul Mawla, project officer of the Payra power plant.
He said the newly-built RNPL power plant will begin production on a trial basis in January.
As such, power generation at the Payra power plant was halted to allow testing of the transmission lines of the new facility in Amtoli upazila of Barguna, he said.
The new plant is located on the banks of the Ramnabad river, just two kilometres north of the Payra power plant. Costing about $2.5 billion, its construction began in 2019 on some 950 acres of land.
The RNPL is a joint venture of Bangladesh's state-owned Rural Power Company Limited and China's state-owned Norinco International Cooperation Limited, with each having an equal stake.
To enable the test for commissioning the RNPL-run plant, the authorities of the Payra power plant allowed for their thermal power transmission lines to be kept shut, he added.
Selim Bhuiyan, managing director of the RNPL, said each unit of the two units of the new power station can produce up to 660 MW of electricity.
"But to begin operations, it is now necessary to conduct the test. For this, the Payra-Gopalganj 400 kV power transmission line will have to be shut down. Then, it will take up to 75 days for the commissioning," he added.
Bhuiyan also said they expect the new plant to begin contributing to the national grid on the first week of March and production at its second unit of equal capacity was expected to begin by the end of May.
Sources close to the project said the total installed capacity of the grid-based power plants in the country is about 27,740 MW.
Of this, the capacity of coal-based power plants is 5,683 MW. If the capacity of the RNPL-run plant is added, the total capacity of coal-based power plants would stand at 7,000 MW, they said.
Regarding coal stocks for the new power plant, Bhuiyan said when the plant starts generating electricity, 12,000 tonnes of coal would be required on an average per day for the two units.
An agreement has already been reached with Singaporean company Yantai to supply 1 million tonnes of coal.
Under that agreement, 1.28 lakh tonnes of coal have reached the new power plant. More coal will arrive in January. In this way, coal will be imported in phases according to demand.
He said in an attempt to minimise environmental damage, high-quality coal from Indonesia would be used in this new plant. It is a state-of-the-art power plant, where more electricity will be generated by burning less coal compared to conventional power plants.
Regarding the price of electricity, he said the production cost of this new plant will be lower than that of Adani, Rampal, Banshkhali and other thermal power plants.
Considering the current price of coal ($77), the price of electricity per unit can be around Tk 9.85 on an average.
Md Toufiq Islam, project director and chief engineer of the RNCL-run plant, said if everything goes well, the first unit would be fully operational by early March and the second unit by June.